HomeMy WebLinkAboutItem #40 - Discussion ItemKI
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
31
To Honorable Mayor and DATE AUGc 1 9� F`LE
Members of the City Commission J
SUBJECT Scattered Site Housing -
Model City Phase III
Increase in Contract
FROM REFERENCES
i
j CeENCLOSURES
s io
C i t ag er
RECOMMENDATION
It is respectfully recommended that the City Commission adopt the
attached Resolution authorizing increase in the contract between
Robinson Construction, Inc. and the City of Miami for Scattered
Site Housing Homeownership Development Program - Model City Phase
III, not to exceed $34,000; and further ratifying the City
Manager's written finding that the increase resulted from
emergency circumstances.
BACKGROUND
The Department of Public Works, in an effort to serve all
residents of the City of Miami, has determined that it is now
appropriate and in order for the City Commission to ratify the
City Manager's decision to increase a contract dated February 27,
1990, between the City and Robinson Construction, Inc, for
construction of Scattered Site Housing Homeownership Development
Program -- Model City Phase III B--3240--C, in the amount not to
exceed $34,000 for necessary extra work, and to ratify the City
Manager's emergency finding that allowed the extra work to
continue on all three projects.
The City Commission awarded a contract to Robinson Construction,
Inc, for the construction of Scattered Site Housing Homeownership
Development Program -- Model City Phase III, Project No. 321034 in
the amount of $85,500, on October 12, 1989. Generally, the
project consisted of the construction of two, three --bedroom, two --
bathroom, single --family residences on City owned scattered
housing sites. As the construction progressed, some unexpected
conditions developed for the small -firm contractor which affected
the construction costs. These conditions are outlined below:
3 .1,'
Se 0S511) nJ
r
1. The scattered site locations had unforeseen security ,
problems which in many instances required the contractor to
replace and redo phases of the work due to vandalism and
theft.
2. The locations required sidewalk and curb and gutter
replacement work that was not anticipated by the contractor.
3. Window specifications were revised to satisfy building code
requirements which resulted in extra costs for the houses.
4. Site clearing and haul --off of illegally dumped debris were
required for some of the locations.
5. Building material costs escalated and increased for the
contractor since being awarded the contracts.
6. Electric service to the houses had to be revised from that
originally shown on the architect's plans.
The above items caused delays in the scheduled completion of the
houses. The City was allocated specific surtax mortgage
financing for the prospective home buyers. Work on the subject
houses was underway, and in several cases, prospective buyers
were identified when the contractor requested additional monies
to complete the houses. Further delays in construction would
impact the prospective buyers and place the City at risk of
having Dade County's Documentary Surtax Advisory Board rescinding
mortgage funds. It was decided that the most cost effective and
expeditious manner to address all of the above problems was to
allow Robinson Construction, Inc. to proceed with the extra work
and complete the construction of the houses as soon as possible.
Funds are available for the aforesaid contract increase from
monies already appropriated to the project in the City's Capital
Improvement Appropriate Ordinance No. 10642, Project No. 321034.
93- 549.1
CITY OF' •MiAMI, FLORIDA
INTER -OFFICE MEMORANDUM
-, Cesar H. Odio oATE: December 9, 1991 FILE B-324C
City Manager .
i SUaJECT: Scattered Site Housing -
w Model City Pnase III
Contractor Failing To Complet
r4oM V REFERENCES : Houses As Planned
La' Prieto-Portar, Ph.D., P.E.
Di r et f o r of P u b l i c W o r K 5 ENCLOSiJRE3
Robinson Construction, Inc. was awarded two contracts to
construct six (6) houses with four mouses and two houses
respectively per contract. The worK began on the contracts in
1990 with a planned slow down due to lacK of potential buyers.
Prospective buyers were subsequently identified and completion
schedules adjusted witm the contractor for second quarter in 1991
completion. The contractor continued to fall further behind and
did not snow sufficient progress. In August 1991 three mouses
were deleted from Robinson Construction's contract and awarded
informally, on an emergency basis, to anotner contractor.
Robinson presently is unable to complete two houses next to each
other at 1741 A/B N.W. 55 Street along with a third house at 5845
N.W. 12 Avenue witnout an increase in contract.
Tne Department of Development b Housing Conservation has secured
financing for the prospective buyers for the three homes. There
exist an emergency need to complete the houses to avoid losing
the financing available for the prospective buyers. The
financing is available through December 31, 1991. Public WorKs
request your authorization to taKe the following steps to ensure
that the nouses are completed by the required deadline:
1.
2.
Manage the remaining worK by directing the
contractor's scheduling of trade worK (e.g. all
materials and labor) and controlling further
authorization of payments for materials and
subcontract worK.
Establish procedure with City Finance Department,
Accounts Payable and Housing Department, to issue
co -payment cheeKs to Robinson Construction and
suppliers and subcontractors.
- 1 -
3
Cesar H. Odio
City Manager
December 9, 1991
Page 02
3. Proceed with above items 1 and 2 to finish the
houses by increasing the contracts by $40,000 as
detailed below:
PROJECT DESCRIPTION CONTRACT
SCATTERED SITE HOUSING AMOUNT INCREASE +% INCREASE
Model City Pnase II Job
B-3240-B (1 mouse) $42,800 $20,000 +46.7%
Model City Phase III Job
8-3240-E (2 mouses) $85,500 ftOs,00d +23.4%
Totals $138,300 $40,000 +31.2%
Final construction cost for the one (1) home to be constructed
under the Model City Phase II (8-3240-8) with the $20,000
increase in contract is estimated at $62,800. Moreover, the
final construction cost for the two (2) hopes to be constructed
under the Model City Phase III (8-3240-C) with the $20,000
Increase in contract is estimated at $105,500 or $52,750 per
unit. The price for eacn of the 3-bedroom 2-batn unit is
$59,900. Base on the selling price of $59,900 per unit, the City
will still be able to recoup the additional $40,000 which is
required to complete the construction of the three (3) new single
family planned under Model City Phase II and III.
Development and Housing has advised Public Works that the
additional $40,000 is available to increase the contracts as
detailed above.
APPROVED:
CITY MANAGER
JHJ:au
cc: Carlos E. Garcia, Finance Department
Herbert J. Bailey, Development 8 Housing Conservation Dept.
Jeffrey 8. Hepburn, Development & Housing Conservation Dept.
', 93 •
.. � V: 1'wA t V4i AI�u I�ItatEIET� Q� T�� C4MMISSIQ
R. Y. I.
CITY OF..MIAMI, FIR PSM1'. 4L DATE_
INTER -OFFICE MEMORANDUM
Cesar H. Odio LATE March 10, 1992 C'LE B-324C-
City Manager
SUaJECT Scattered Site Housing -
Model City Phase III
/ Increase In Contract
REFERENCES
Waldemar E. Lee
Acting Director of Public Works ENCLOSURES
Public Works has been directing the construction of two (2)
houses under construction by Robinson Construction. Inc. The
houses are located at 1741 A & B N.W. 55 Street. The contractor
has had many problems completing the houses primarily due to lack
of financing and mismanagement. The prospective buyers for these
two houses have been waiting for some time to close on the
houses. They have been granted extensions by the City and
Citibank Savings on consummation of the purchase of the houses
because of the construction delays which has created problems for
the home buyers.
Through efforts of Public Works the houses presently have
plumbing and electrical Building and Zoning Department final
inspections. The air conditioning units will be set this week
and the Certificate of Occupancy is expected to follow. Back in
December, 1991, Public Works received your approval to direct and
manage the contractor in a detailed task approval -for -payment
manner. That has been done with dual party checks issued for
work on the houses. The contract was increased by $20,000 to a
total of $105,500 (2 houses). The final cost of the houses will
increase another $14,000. This brings the total construction
cost to $119,500, and $59,750 per house.
The Department of Development and Housing Conservation has worked
very closely with Public Works on the situation of Robinson
Construction difficulty in building the houses. The Department
of Development and Housing Conservation has advised Public Works
that the additional funds are available for the increase. We
hereby request your approval deeming this an EMERGENCY NEED to
increase the contract an additional $1I*,) A00v
APPROVED:
CITY MANAGER
DCB,au
cc: --Carlos E. Garcia, Finance Department
Herbert J. Bailey, Development & Housing Conservation Dept.
Judy S. Carter, Chief Procurement Officer, GSA/S.W. Dept.
Jeffery B. Hepburn, Development & Housing Conservation Dept.
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
I
TO: Matty Hirai DATE July 19, 1993" FILE B--3240--C
j City Clerk
SUWECT SCATTERED SITE HOUSING --MODEL
i CITY PHASE III
Increase in Contract
_ Request to Publish Notice for
FROM �.� REFERENCES Public Hearing
Waldemar E. Lee
Director of Public Works ENCLOSURES
I
Please make arrangements to publish a Notice of Public Hearing
for objections to a proposed increase in the contracts with
Robinson Construction, Inc. for construction of Scattered Site
Housing Homeownership Development Program --Model City Phase III
for the Commission Meeting of September 9, 1993•
DCB:au
ee: City Clerk
Tax & License
Cost Analysis
Contract B--3240--C
Approved:
r Aurelio Perez--Lugones
�j Legislative Administrator
a 3— 19. 1
CITY OF MIAMI, FLORIDA
NOTICE TO THE PUBLIC
j A public hearing will be held by the Commission of the City
of Miami, Florida, on September 9„ 1993, at a.m. in the
City Commission Chambers at City Hall, 3500 Pan American Drive,
Miami, Florida, for the purpose of hearing any objections from
any interested parties affected by an increase in the contract
between Robinson Construction, Inc. and the City of Miami in an
amount not to exceed $34,000 for necessary extra work at
Scattered Site Housing Homeownership Development Program --Model
City Phase III, B•-3240--C, Project No. 321024; and in ratifying
the City Manager's finding that the aforesaid increases resulted
from emergency circumstances.
All interested persons are invited to appear and may be
heard concerning these items. Should any person desire to appeal
any decision of the City Commission with respect to any matter
considered at this hearing, that person shall ensure that a
verbatim record of the proceedings is made, including all
testimony and evidence upon which any appeal may be based.
(City Seal) Matty Hirai
City Clerk
Miami, Florida
93- 5.19.1
J-93-607
8/23/93
RESOLUTION NO.
A RESOLUTION AUTHORIZING AN INCREASE, IN AN
AMOUNT NOT TO EXCEED $34,000.00, IN THE
CONTRACT BETWEEN THE CITY OF MIAMI, FLORIDA,
AND ROBINSON CONSTRUCTION, INC., DATED
FEBRUARY 27, 1990, FROM $85,000.00 TO
$119,000.00, FOR THE SCATTERED SITE HOUSING
HOMEOWNERSHIP DEVELOPMENT PROGRAM -MODEL CITY,
PHASE III, B-3240-C, CAPITAL IMPROVEMENT
PROJECT NO. 321034; AUTHORIZING SAID FUNDS TO
BE PROVIDED FROM CAPITAL IMPROVEMENTS
ORDINANCE NO. 10642 FUNDS ALREADY
APPROPRIATED TO THE PROJECT; FURTHER
RATIFYING THE CITY MANAGER'S WRITTEN FINDING,
BY AN AFFIRMATIVE VOTE OF 4/5THS OF THE
MEMBERS OF THE CITY COMMISSION, THAT THE
HEREIN INCREASE RESULTED FROM EMERGENCY
CIRCUMSTANCES.
WHEREAS, there exists a contract dated February 27, 1990,
between the City of Miami, Florida and Robinson Construction,
Inc., for Scattered Site Housing Homeownership Development
Program -Model City, Phase III, B-3240-C, Capital Improvement
Project No. 321034; and
WHEREAS, an increase, in an amount not to exceed $34,000.00,
for the aforesaid contract is required to cover the cost of
necessary extra work involving unforeseen theft, vandalism and
other security problems; replacement of deteriorated sidewalk,
curb and gutters not included in the original contract; revisions
to window specifications to satisfy building code requirements;
l/
93- 549.1
increase to be provided from monies already appropriated to the
project.
Section 3. This Resolution shall become effective
immediately upon its adoption.
PASSED AND ADOPTED this - day of 1993.
ATTEST:
MATTY HIRAI
CITY CLERK
CAPITAL PROJECT REVIEW:
1.
EDUARDO RODRIGUEZ
CAPITAL IMPROVEMENT MANAGER
DEVELOPMENT AND HOUSING CONSERVATION
REVIEW:
1-51
JEFFERY B. HEPBURN
i ASSISTANT DIRECTOR
PREPARED AND APPROVED BY:
CARMEN L. LEON
ASSISTANT CITY ATTORNEY
CLL:esk:M3812
i
XAVIER L. SUAREZ, MAYOR
SUBMITTED BY:
WALDEMAR E. LEE
DIRECTOR OF PUBLIC WORKS
APPROVED AS TO FORM AND
CORRECTNESS:
a��7 --v7 !- /r
. Q N S, III
CITY ATT Y
030'��
93— 19. a