HomeMy WebLinkAboutItem #02A - Discussion ItemFebruary 25, 1993
Mr. Cesar H. Odio
City Manager
City of Miami
3500 Pan American Drive
Miami, Florida 33133
CUR
� ��
METRO-DADE CENTER
OFFICE OF COUNTY MANAGER
SUITE 2910
111 N.W.lot STREET
MIAMI, FLORIDA 33128-11*1
(M) 376-5311
record in c * I- c ;. i a p i lh
atty Hirai
City Cle-T.k
RE: Sanitary Sewer Service Agreement Restrictions
Dear Mrtr:
This shall acknowledge receipt of your letter of February 12,
1993 concerning the above referenced matter. Unfortunately,
I will not be able to attend your meeting of February 25 due
to prior commitments. As an entity also affected by this
prohibition, we in Dade County are keenly aware and
understand the difficulties this situation presents. We
welcome this opportunity to share with you the conditions
that precipitated this action and the rationale used by
County officials in determining its implementation.
We have prepared a response for each of the six questions
which you posed in your letter. For the sake of clarity, we
have used the same order and numbering system in which they
were presented. As you will see from these responses and as
has been discussed with you and your staff previously, Dade
County did not hide this situation or its magnitude. The
problems with the sewer system, in particular the bay
crossing, have been the subject of numerous public meetings,
newspaper articles and other media presentations and a Grand
Jury investigation. The City and its officials have been a
part of this process from the very beginning. Therefore, it
seems to me that this situation should not have come as a
surprise to City officials. Shortly after the State
Department of Environmental Regulation imposed new permitting
requirements for sanitary sewer projects in Dade County, all
affected parties were notified and invited to participate in
the discussions that took place to interpret, assess and
respond to this new state mandate. These points were
discussed at length with you during our meeting of February
17th. As per your request, we are pleased to submit the
following responses to your questions.
1. The January 27, 1993 order by the Director of the Dade
County Department of Environmental Resources Management
prohibiting new sanitary sewer service agreements was
made partly in response to the new, more stringent
permitting requirements imposed by the Florida
Department of Environmental Regulation (FDER) on
November, 1992 for sewer construction projects within
Dade County. In particular, these new requirements
established guidelines which, based on flow data and
Di -S(_us slog
other documented facts, can not be met in certain areas -
within the County. On December 10, 1992, after -a number
of clarification meetings with FDER, the County
notified utility officials, building officials and
consultants about these new state requirements (copy
attached). On December 23, 1992, a meeting with
consultants and utility officials was held to discuss
the new state requirements. In the meantime, data was —
gathered and analyzed to determine those areas of the
County which could be adversely affected by the new
state requirements. Based on our analysis of the data, _
the County determined that this measure would avoid
lengthy and costly engineering studies which at their
conclusion would have shown the inability of the system
to comply with the new state requirements.
2.
The sanitary sewer service agreement prohibition applies
to those areas of Dade County designated as "Critical
Sewer Service Areas". As indicated in the map dated _
January 25, 1993 (copy attached), these areas include
regions other than the Central District. Information --
currently available from other areas of Dade County does
not indicate the existance of capacity problems
elsewhere. However, it should be noted that as more
information becomes available or as existing problems —
are corrected, the boundaries of these "Critical Sewer
Service Area" will change, either expanding or —
contracting based on the data gathered.
3.
We are currently negotiating with FDER and anticipate a
settlement in a few months. Meetings have been
scheduled at the following dates and locations:
March 18 and/or March 19 - Tallahassee _-
April 15 and/or 16 - Gainesville
_
Mav 20 and/or 21 - TBA
4.
The County has planned its wastewater treatment plant
and facilities expansion program in accordance with its _
regional Wastewater Facilities Plan. This plan was
prepared by engineering consultants in the mid-1980's,
and was approved in 1987 by FDER and the U.S.
•
Environmental Protection Agency (EPA) after extensive
,�
M d j4
review. The majority of the facilities proposed under
that plan have either already been constructed, are
,:.-.
under construction or are to be designed in the near
p., v
future.
p U
Cl
Despite the planning and construction of major treatment
facilities over the past decade, the County has
experienced sewage flows which have increase more than
o
population growth. Sewer system evaluation and survey
(SSES) studies performed in the 1970's recommended
�i 4
specific repair work to reduce infiltration and inflow
�
and that work which was identified as cost effective was
completed. The County's on -going infiltration/inflow
(I/I) program was further accelerated in 1990. A
priority list of collection systems with the highest I/I
D
was compiled based on pumping data, chloride content of
sewage, and metered flow during late night hours in the
wet and dry seasons. All pipelines with leaks will be
93— 121-1
i
either chemically grouted, replaced or sliplined.
As you may be aware, combined sewers (stormwater
connections to the County's sanitary sewer system) have
been identified as a major source of inflow. Your city,
along with other agencies, has responded to our requests
to disconnect these combined sewers. However, we
continue to discover new connections with our on -going
investigations and their disconnections are being
pursued through the efforts of regulatory agencies.
5. During the past five years, the County has completed a
number 'of wastewater projects in the City of Miami.
These projects include slipl.ining of gravity
interceptors, replacement of inverted siphons,
installation of telemetry monitoring system,
construction of pumping station 33-P1, and
rehabilitation of the 4th Street pumping station at an
approximate cost of $16 million. In addition to the
above projects, the Department has an extensive in-house
I/I program utilizing nine TV and Grout crews. The
County has budgeted capital expenditures of
approximately $9 million for the next two fiscal years
solely for I/I work, with similar amounts estimated to
be budgeted in succeeding ,years.
Most recently, the Department contracted with Ric -Man
International, Inc:. to perform TV and Grouting services
along the banks of the Miami River at a cost of $1..5
million. This project is on -going. In addition, a new
contract will be let next month for a similar effort in
the northwest area of the City at an estimated cost of
$2 million. Furthermore, a recently -executed contract
with a consulting engineer to update the Departments'
Wastewater Facilities Plan will include additional I/I
work, concentrating initially in the Central District
area.
6. The County's three treatment plants are interconnected
allowing for a partial diversion of flows. However,
capacity at the North and South plants is limited and
additional diversions are not possible. A major
transmission main is currently under construction in the
North District area (N. 24) and upgrades to selected
pumping stations are being designed.
We trust that these responses clarify the issues to your
satisfaction. In closing, let me state that we appreciate
the statements of support which we have received from the
City in this matter, and welcome your assistance in the
resolution of this situation.
Submitted into the public
S'ncerely,
record in connection with
Jo uin G . Avino, P . E . , P.L.S. item C
County Manager orl �" �fB
Attachments
chatty Hirai
City Clerk
93- 121• 1
METROPOLITAN DADE , LINTY, FLORIDA
METF1d'-iIhDE Snbznitted into the Pubic 0
?
inCOrl11E? METRE?-DADE CENTER record i
item gqFNVIRONMENTAL REStlUitt'ES MANAMMM
SUM WO
• 111 w.w.1I1 STREET
MIAMI, FLORIDA 33120-1971
DATE: DECEMBER 10, 1992 M attY Hirai (305) 3753376
City' Clerk
TO: BUILDING OFFICIALS, UTILITY OFFICIALS AND SANITARY
SEWER CONSULTANTS IN DADE COUNTY
FROM: JOHN W. RENFROW, P.E.
y
DIRECTOR
ENVIRONMENTAL RESOURCES EMENT
RE: NEW PROCEDURES AND REQUIREMENTS FOR OBTAINING STATE
APPROVAL OF SANITARY SEWER COLLECTION/TRANSMISSION
SYSTEMS WITHIN DADE COUNTY
THIS- SHALL SERVE TO NOTIFY YOU OF NEW PROCEDURES AND
REQUIREMENTS CURRENTLY IN EFFECT WITHIN DADE COUNTY FOR
OBTAINING STATE APPROVAL OF SANITARY SEWER COLLECTION/TRANS—
MISSION SYSTEM CONSTRUCTION PROJECTS.
THE FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION (FDER) HAS
MADE A PRELIMINARY DETERMINATION THAT THE EXISTING WASTEWATER
COLLECTION AND TRANSMISSION FACILITIES SERVING DADE COUNTY
ARE INADEQUATE TO CONVEY PEAK FLOWS. BECAUSE OF THEIR CONCERN
AND IN ACCORDANCE WITH THE PROVISIONS SET FORTH IN RULES
17-4.070 AND 17—4.530(2), FLORIDA ADMINISTRATIVE CODE, FDER
HAS DECREED (SEE ATTACHED LETTER DATED NOVEMBER 16, 1992)
THAT EFFECTIVE IMMEDIATELY AND UNTIL FURTHER NOTICE,
APPLICATIONS FOR CONSTRUCTION OF NEW WASTEWATER COLLECTION
AND TRANSMISSION FACILITIES CANNOT BE APPROVED BY THE USE OF
A "GENERAL PERMIT`. INSTEAD, NEW PROJECTS MUST SUBMIT A FULL
CONSTRUCTION PERMIT APPLICATION (FDER FORM 17-604.900(1),
APPLICATION TO CONSTRUCT DOMESTIC WASTEWATER COLLECTION AND
TRANSMISSION SYSTEMS). THE OBJECTIVE OF THESE NEW
REQUIREMENTS IS TO ENSURE THAT NEW FACILITIES ARE DESIGNED,
CONSTRUCTED AND OPERATED IN COMPLIANCE WITH APPLICABLE RULES
AND REGULATIONS AND, MORE IMPORTANTLY, THAT THERE IS ADEQUATE
DOWNSTREAM CAPACITY TO PREVENT OVERFLOWS AND FLOODING DURING
PEAK FLOW CONDITIONS. THESE NEW PROVISIONS ARE IN EFFECT
COUNTY WIDE.
PURSUANT TO THE PROVISIONS OF THE DELEGATION AGREEMENT
BETWEEN DADE COUNTY AND THE STATE, DERM WILL PROCESS AND
REVIEW THESE APPLICATIONS AND ISSUE, WHEN WARRANTED, THE
CONSTRUCTION PERMITS. ATTACHED YOU WILL ALSO FIND A PACKAGE
PREPARED BY OUR STAFF WHICH CONTAINS THE AFOREMENTIONED
APPLICATION FORMS, INSTRUCTIONS AND' -GUIDELINES FOR THE
ENGINEERING REPORT WHICH MUST ACCOMPANY EACH NEW APPLICATION.
THESE GUIDELINES ARE INTERIM IN NATURE AND MAY BE MODIFIED AS
A RESULT OF FURTHER REVIEW AND COMMENTS: FURTHERMORE, THE
DEPARTMENT IS IN THE PROCESS OF IDENTIFYING THOSE AREAS
WITHIN THE COUNTY WHICH HAVE AND DO NOT HAVE AT PRESENT
93- 121•-
4
SUFFICIENT CAPACITY TO ACCOMODATE ADDITIONAL FLOWS. IT IS
ANTICIPATED THAT IN THE COMING WEEKS THE DEPARTMENT WILL
SOLICIT YOUR INPUT ON THESE MATTERS, AND WILL BE ISSUING
REVISED GUIDELINES AND FURTHER INFORMATION ON THIS TOPIC.
THESE EFFORTS WILL BE GEARED TO ENSURE. COMPLIANCE WITH
APPLICABLE RULES, REGULATIONS AND MANDATES WHILE MINIMIZING
ADVERSE: IMPACTS TO THE COMMUNITY.
SHOULD YOU HAVE ANY QUESTIONS REGARDING THESE PLATTERS, PLEASE
CONTACT THE WASTEWATER SECTION OF THE DEPARTMENT AT 375-3308.
ATTACHMENTS
Submitted into the public
record is connection vnith
item S-1 on_� a S
Matte Hirai
City Clerk
93- 121•1