HomeMy WebLinkAboutR-96-0047J-96-76
1/9/96 9 6 ` 47
RESOLUTION NO.
A RESOLUTION AUTHORIZING AN INCREASE IN THE
AMOUNT NOT TO EXCEED $5,346.96 IN THE
CONTRACT BETWEEN THE CITY OF MIAMI, FLORIDA,
AND R. L. SAUM CONSTRUCTION CO., AUTHORIZED
BY RESOLUTION NO. 95-541, FROM $1,059,374.45
TO $1,064,721.41, FOR THE ORANGE BOWL
MODERNIZATION PH. III SUPERBLOCK
DEVELOPMENT - NORTH, PROJECT B-62431
ALLOCATING FUNDS THEREFOR AS PREVIOUSLY
APPROPRIATED BY ORDINANCE NO. 11205, AS
AMENDED, FROM CAPITAL IMPROVEMENT PROJECT NO.
404240.
WHEREAS, there exists a contract between the City of Miami,
Florida and R. L. Saum Construction Co. for the construction of
Orange Bowl Modernization Ph. III Superblock Development - North,
Project B-6243, with allocated funds as amended in Capital
Improvement Project No. 404240; and
WHEREAS, an increase in the contract not to exceed $5,346.96
is required to cover, the cost of extra work required for
elevation correction to assist in water dissipation; and
f
WHEREAS, the Director of Public Works, the Coordinator of
i
Capital Improvement and the City Manager recommend the increase
in contract to cover the additional costs; and
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY,
OF MIAMI, FLORIDA:
I'
}i
r
Section 1. The recitals and findings contained in the
Preamble to this Resolution are hereby adopted by reference
thereto and incorporated herein as if fully set forth in this
Section.
Section 2. The contract between the City of Miami,
Florida and R. L. Saum Construction Co., for the construction of
Orange Bowl Modernization Ph. III Superblock Development - North,
Project B-6243, is hereby increased in an amount not to exceed
$5,346.96, from $1,059,374.45 to $1,064,721.41, with funds for
the increase to be provided from Capital Improvement Project
No. 404240.
Section 3. This Resolution shall become effective
immediately upon its adoption.
PASSED AND ADOPTED this 25th day of January 1996.
i
' e
STEP EN P. CLARK, MAYOR
-2-
Ai
r
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
43'
To ` Honorable Mayor and DATE : ��,�,, FILE
Members of the City Commission
FROM :
Cesar 14W?
City
SUBJECT : ORANGE BOWL
MODERNIZATION - PH. III
SUPERBLOCK DEVELOPMENT
REFERENCES : NORTH
INCREASE IN CONTRACT
ENCLOSURES:
I
RECOMMENDATION
It is respectfully recommended that the City Commission adopt the
attached Resolution authorizing an increase in the contract
between R. L. Saum Construction Co. and the City of Miami for
Orange Bowl Modernization Phase III, Superblock Development -
North, Project B-6243, in the amount of,$5,346.96.
BACKGROUND
`.r'he City Commission, at its meeting of July 13, 1-095, adopted
Resolution No. 95-541 authorizing a contract, under CIP Project
Na. 4.04240, with R. L. .Saum. Const. Co. for the construction of
Orange Bowl Modernization Ph. III Superblock Development -North,
i.n the amount of $1,059,374.45.
The contract amount included a construction contingency (i.e.,
cash allowance). The contingency monies have been exhausted and
additional funds are needed to pay for elevation corrections to
assist in water dissipation.
Funds are available in the F/Y 1994-1995 budget in the amount of
$5,346.96 from CIP No. 404240.
n i
V '
1
96- 47
S--c3 G... F.R I. 1 0 C 3 7
1
J-95-579
06/16/95
RESOLUTION NO.9 5 - 5 4 1
A RESOLUTION, BY A 4/5THS AFFIRMATIVE VOTE OF
THE MEMBERS OF THE CITY COMMISSION AFTER A
DULY ADVERTISED PUBLIC HEARING, RATIFYING,
APPROVING AND CONFIRMING THE CITY MANAGER'S
FINDING OP AN EMERGENCY SITUATION REQUIRING
THE EMERGENCY CONTRACTING OF GOODS AND
SERVICES IN THE TOTAL AMOUNT OF $1,359,191.25
FOR THE PROJECT ENTITLED "ORANGE BOWL
MODERNIZATION PHASE III, SUPBRBLOCK
DEVELOPMENT - NORTH, B-6243111 WITH MONIES
THEREFOR ALLOCATED FROM THS CAPITAL
IMPROVEMENT PROGRAM FISCAL YEAR 1994-95,
INDEX CODS NO. 319302-830, PROJECT 404240 IN
THE AMOUNT OF $1, 3 5 9 ,191. 2 5 TO COVER . GOODS
AND SERVICES AND $169,361.48 TO COVER THE
ESTIMATED EXPENSES FOR AN ESTIMATED .TOTAL
PROJECT COST OP $1,528,552.73.
P 0 1
WHEREAS, the City of Miami is committed to the University of
Miami to develop a "campus -like" setting for the site around the
Orange Bowl Stadium prior to the 1995 football season; and
WHEREAS, Urban Architects, Inc., acting as the Consultafits
fortheOrange Bowl, were directed to prepare a Master Plan for
the site improvements of the Stadium as well as an estimated
construction cost to develop the project in several phases; and
WHEREAS, based upon the conceptual design prepared by Urban
Architects, Inc., the Department of Public Works prepared the
construction plans for the phase to be built in 1995; and
CIi'Y cobMSSION
)0ErJTG OP
J U L 13 1995
Resolution N
95- 1
96- 47
3
r
I
P 0 2
WHEREAS, because of the time restrictions imposed by the
beginning of the 1995 football season, the 1995 project was split
into two parts; The first part includes the actual .site work
improvements, and the second part includes th6 purchase of goods
that are to be fabricated by the manufacturer and installed on
1
site; and
WHEREAS, on May 17, 1995, the Department of public Works
solicited bids for the project named "Orange Bowl Modernization
Phase III,. Superblock Development North, B-6243", for the
i construction of the site improvements; and
WHBRRAS, sealed bids were received on June 6, 1995 for the
i
"Orange Bowl Modernization Phase 111, Superblock Development -
North, B-6243; and
WHEREAS, the City Manager and the Director of the Department
of Public Works recommended that the bid from R. L. Scum
Construction Co. be accepted as the lowest responsible and
responsive bid; and
WHEIZW , the City Manager directed the Public Works
Department to purchase on an emergency basis, several specialty
items that are to be fabricated to order so they may fit :the
specific requirements of the design; and
WHEREAS, the following goods and services were contracted to
the listed suppliers, on an emergency basis:
R. L. Saum Construction Co. $1,059,374.4S
Construction of Site Improvements
Mardan Fabricators $36,500.00
' Supply and installation of three
' (3) 'Ticket booths
'
96
f
S
i
ARD Rolling Doors
$39,890.80
Supply and installation of nine
(9) roll -up doors
Design Awning and Structures
$96,000.00
Supply and installation of three
t3) canopies with frames
i
Consolidated glectric Supply
$43,550.00
Supply of two (2) high masts
polies and lights
i Paramount Electric Dist.
$50,766.00
Supply of Promenade lighting
South Dade Electric Supply
419,110.00
Canopies lighting system
Urban Architects Inc.
$24,000.00
Professional Fees for Conceptual
Design
P . 0 Z
NOW, THEREFORE, HB IT RNSOLvED BY THS CommISSION OF THB CYTy
OP MIAMI, FLORIDA:
s
Section 1. The recitals and findings contained in the
Preamble to this Resolution are hereby adopted by reference
thereto and incorporated herein as if fully set forth in this
t
Section,
II; Section 2, By a 4/5ths affirmative vote of the members
f of the City Commission, after a duly advertised public hearing,
.t
the City Manager's finding of an emergency situation requiring
the emergency contracting of goods and services in the total
amount of $1,359,191.25 for the project entitled "0range Bowl
f; j Modernization Phase III, Superblock Development - North, e-62430,
i
is hereby ratified, approved and confirmed, with monies therefor
allocated from the Capital Improvement program Fiscal Year
2994-95, Index Code No, 319302-830, Project 404240 in the amount
t
i
I -
5
96- 4'7
r'�
�i
f
I
1
6
i
P . 0 4
of $1,359,191-25 tG cover goods and services and $169,361.48 to
cover the estimated expenses for an estimated total project cdst
of $1,528,552.73.
Section 3. This Resolution, shall become effective
immediately upon its adoption.
s PASSED AND AIPOP't`8D this 13thday of JuIY , 1995.
!;TEPINS P. CLARK, YOR.
i A'ITECWT :
ER
8R .7. FOs
CITY CLERK
SUBMIT= BY
(4
i WALDEMAR H. LEE, DIR$CTOR
DEPARTMENT OF PUBLIC WORKS
s
CAPiThL PROJ C'T IEW
j DR QuEz, DIRECTOR
ASSET MAXAGEMBNT AND
CAPITAL I14PROVEMENTS
f
LEGAL RSVIEW BY:
C . MWAM MAER
C918F ASSISTANT CITY ATTORNEY
APPROVED AS TO FORM AND CORRECTNESS:
A. t�vc o x fi
CITY A' Y
r
I CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
TO : W�ii 1 l:er J . Foeman DATE January 4 , 19 °? 6 FILE
C iA y Clerk
suaiEcr Request to Publish
i Notice of Public Hearing/
j Orange Bowl Modernization
FROM REFERENCES . Phase IIIr Superblock
Waldemar E. .Lee, Director Development - NORTH
1.1tiblic works Department ENCLOSURES:
"'1n_ase make arrangements to publish a Notice of Public Hearing
[or discussions pertaining to a proposed increase in the contract
with R. L. Saum Const. Co. for the construction of a. new Parking
Area (North Side) at the Orange Bowl Stadium, Project B-6243, CIP
Nrl. 404�.40.
'ih(� Public- hearing has been scheduled for January 25, 1996.
to index code 319202-287 .
M
Civil Engineering (Highways)
Central
Zvi Gallastegui
Agenda Coordinator
96- 47
r
CITY OF MIAMI, FLORIDA
NOTICE OF PUBLIC HEARING
A public hearing will be held by the Commission of the City of
Miami, Florida, on January 25, 1996, at 9:00 a.m. in the City
Ccmimission Chambers at City Hall, 3500 Pan American Drive, Miami,
Florida, for the purpose of hearing any objections from any
interested parties affected by an increase in the contract
between R. L. Saum Const. Co. and the City of Miami in an amount
not to exceed $5,346.96 for the construction of a new ,Parking Lot
area (North Side) at the Orange Bowl Stadium, Project B-6243, CIP
Nei. 404240.
All interested persons are invited to appear and m.a. be heard
cnnce.r_ning this matter. Should any person desire to appeal any
decision of the City Commission with respect to any matter
considered at this hearing, that person shall ensure that •a
verbatim record of the proceedings is made, including all
testimony and evidence upon which any appeal may be based.
Walter Foeman
City Clerk
Miami, Florida
96- 47