RESOLUTION NO . 9 8_ 1 0 3 6
A RESOLUTION, BY 4/5THS AFFIRMATIVE VOTE OF
THE MEMBERS OF THE CITY COMMISSION,
RATIFYING, APPROVING AND CONFIRMING THE CITY
MANAGER'S FINDING OF AN EMERGENCY, AND
APPROVING THE AWARD OF A CONTRACT TO WEISS &
WOOLRICH SOUTHERN ENTERPRISES, INC., FOR THE
"COCONUT GROVE CONVENTION CENTER OFFICE ROOF
REPLACEMENT, B-6304" PROJECT; ALLOCATING
FUNDS THEREFOR IN THE AMOUNT OF $42,000.00 TO
COVER THE CONTRACT COST AND $4,080.00. TO
COVER THE ESTIMATED EXPENSES, FOR AN
ESTIMATED TOTAL AMOUNT OF $46,080.00, AS
APPROPRIATED BY THE FY 1997-1998 CAPITAL
IMPROVEMENT ORDINANCE NO. 11623, AS AMENDED,
PROJECT NO. 325006;
WHEREAS, the Coconut Grove Convention Center office roof had
several interior leaks and needed immediate repair; and
WHEREAS, on August 18, 1998, the Department of Public Works
received formal sealed bids for the project entitled "Coconut
Grove Convention Center Office Roof, B-6304 and the contract for
the project was awarded on an emergency basis; and
WHEREAS, the lowest and most responsive bidder was Weiss &
Woolrich Southern Enterprises, Inc.; and
WHEREAS, the roof replacement was needed immediately and
before the bid acceptance could be placed on the next commission
agenda for approval; and
WHEREAS, the Department of Public Works wishes to ratify,
MY coma3smn
FETING OF
OCT 13M98
Rewluum .
98-19JG.
approve, and confirm the award of this emergency contract award;
and
WHEREAS, the City Manager and the Director of the Department
of Public Works recommend that the bid from Weiss & Woolrich
Southern Enterprises, Inc., be accepted as the lowest responsible
and responsive bid; and
WHEREAS, funds for said were appropriated by the
FY 1997-1998 Capital Improvement Ordinance No. 11623, as amended,
under Project No. 325006;
NOW, THEREFORE, BE IT RESOLVED BY THE COMMISSION OF THE CITY
OF MIAMI, FLORIDA:
Section 1. The recitals and findings contained in the
Preamble to this Resolution are hereby adopted by reference
thereto and incorporated herein as if fully set forth in this
Section.
Section 2. By a 4/5ths affirmative vote of the members
of the City Commission, ratifying, approving, and confirming the
City Manager's finding of an emergency situation, and approving a
contract award to Weiss & Woolrich Southern Enterprises, Inc.,
for "Coconut Grove Convention Center Office Roof, B-630411, with a
contract cost of $42,000 and estimated expenses incurred by the
City in the amount of $4,080, with funds therefor hereby
allocated from Capital Improvement Project No. 325006.
Section 4. This Resolution shall become effective
immediately upon its adoption and signature of the Mayor.1/
PASSED AND ADOPTED this 13th day of October 1 1998.
JOE CAROLLO, MAYOR
In accordance with Miami Code Sec. 2-36, since the Mayor did not indicate approval of
this legislation by signing it in the designated place provided, said legislation ^v'
becomes effective with the elapse of ten (10) days from the date of commission action
ATTEST: regarding same, without the Mayor exerci ' eto.
Waft . F ' man, City Clerk
WALTER J. FOEMAN
CITY CLERK
AP
NDRO VIL
ATTORNEY
W2933:CSK:kc
CORRECTNESS/
1! If the Mayor does not sign this Resolution, it shall become effective at
the end of ten calendar days from the date it was passed and adopted.
If the Mayor vetoes this Resolution, it shall become effective
immediately upon override of the veto by the City Commission.
CITY OF MIAMI, FLORIDA 45
INTER -OFFICE MEMORANDUM
TO : The Honorable Mayor and
Members of the City Commission
FROM Lam/
4nal H. vvaTsnaW
City Manager
RECOMMENDATION
!J.IC?
DATE OCT. : . ., 6 FILE
SUBJECT : A Resolution Ratifying , Approving
and Confirming the City Manager's
Finding of an Emergency -
REFERENCES: OFFICE ROOF REPLACEMENT -
COCONUT GROVE CONVENTION
ENCLOSURES :CENTER
It is respectfully recommended that the City Commission adopt the attached Resolution
ratifying, approving and confirming the findings of the City Manager and authorizing the
EMERGENCY execution of a contract in the amount of $42,000.00 with WEISS &
WOOLRICH SOUTHERN ENTERPRISES, INC., for the project entitled Coconut Grove
Convention Center, Office Roof Replacement, B-6304.
BACKGROUND
The Coconut Grove Convention Center office is seriously deteriorated with numerous
interior leaks which require immediate repair. Due to the serious water intrusion, the
facility Manager was forced to vacate his office. This condition is not only an
inconvenience to staff but a hazard to our prospective clients and visitors.
Because of the time restrictions imposed by the rainy season, the City Manager directed
the Public Works Department to prepare specifications and to receive bids. On August
18, 1998, the Public Works Department received formal bids for this project and the
lowest responsive and responsible bid received was from Weiss & Woolrich Southern
Enterprises, Inc., in the amount of $42,000.00.
It is now recommended that the City Commission adopt the enclosed Resolution
ratifying, approving and confirming the findings of the City Manager and authorizing the
emergency contracting of Weiss & Woolrich Southern Enterprises, Inc., a non -minority
controlled corporation, in the amount of $42,000.00 for the project entitled Coconut
Grove Convention Center Office Roof Replacement, B-6304. Funds are available to
cover the contract cost and for such incidental items as postage, blueprinting, advertising
and reproduction costs.
Q �0
\ ► 'ia�
DHW/RM/rJ
CGCCroofReplacement.doc 9 Q_ 1 0 63- 6
G '
n
TO
FROM
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
Donald H. Warshaw DATE
City Manager
SUBJECT
/ REFERENCES:
Ja4XJ. Kay, Director
Public Works Department ENCLOSURES:
September 1, 1998 FILE :
Resolution Ratifying, Approving
and Confirming Finding of an
Emergency - Office Roof Replacement
Coconut Grove Convention Center
The Public works Department has verified with the Office of Budget and Management
Analysis that funds are available for execution of a contract in the amount of $46,080.00
from fiscal Year 1997-1998, CIP Ordinance 11623, as amended under project 325006.
BUDGETARY REVIEW
ADDITIONAL APPROVALS
'Dipak M. Parekh, Director P, ar aenz-Butler, Adml strator
Office of Budget & Management Analysis CIP
RM/JJK/mm
c: Raul Martinez, Interim Assistant City Manager
CGCCro of R e p lace m e nt. d o c
98-1o;1s
FACT SHEET
DEPARTMENT OF PUBLIC WORKS
DATE 8 / 18 / 1998
Job Number.: B-6304
PROJECT NAME: COCONUT GROVE CONY. CENTER, OFFICE ROOF REPLACEMENT.
CIP Number.: 325006
LOCATION: 2700 SOUTH BAYSHORE DR. MIAMI, FL.
PROJECT MANAGER: Alberto J. Corrales, P.E.
OTHER TYPE: -
FEDERAL PARTICIPATION:
ASSOCIATED DEPARTMENT: Conferences, Conventions & Public Facilities
ASSESSABLE:
EMERGENCY: 0
RESOLUTION No.:
BID REQUEST: FORMAL INFORMAL 0
DESCRIPTION: The work under this contract consist of furnishing all supervision, labor, equipment, tools and
materials to remove the existing roofing materials down to the metal deck and install a single -ply membrane roof system.
(IF NECESSARY. CONTINUE ON THE BACK)
SCOPE OF SERVICES: PUBLIC WORKS
COST OUTSIDE COST (% OF CONST. COST)
SURVEY/PLAT $ $
TESTINGS $ (E) $ (E) %
DESIGN $ $ %
ADVERTISING $ 1,000.00 (E) $ (E)
CONSTRUCTION $ $ 42,000.00 (BID)
CONST. INSP & MANAGEMENT $ 3,080.00 $ 8 %
OTHER: PERMIT FEES $ (E) $ (E)
SUBTOTAL $ 46,080.00 8 %
INDIRECT COSTS (1.43%) (E) (P.w. ENG. FEE)
CONTINGENCIES (5%)
(EC) - EST. CONST. COST $38,500.00 TOTAL $ 46,080.00
(E) - ESTIMATE
CONTRACTOR'S INFORMATION:
CLASS: 0 F7S NON - MINORITY
TYPE OF WORK: Roofing Contractor MINORITY Fe H nF
YEARS OF ESTABLISHMENT: 10 years LICENSE CC-CO14118
NAME: Weiss & Woolrich Southem Enterprises Inc. TELEPHONE: (9S4) 419-9339
ADDRESS: 1431 SW 30 Ave. Deerfield Beach, FI. 33442
CONTACT PERSON: Henry Gembala CLASS: J = JOINT P = PRIME S = SUB
MINORITY: B = BLACK H = HISPANIC F = FEMALE
SUB -CONTRACTORS:
NAMES:
C. Doc W\EXCELOWIMER KEY1H-ICOMFACT SHEET.XLS RETURN TO PUBLIC WORKS AFTER SIGNED
COPIES: ASSISTANT DIRECTORS, COST ANALYSIS, FILE, ASSOCIATED DEFT, CIP MANAGER nnv. wip
98 r 10;
FORMAL BID
COCONUT GROVE CONVENTION CENTER, OFFICE ROOF REPLACEMENT
Project Number: B-6304 CIP Number: 325006
Project Manager: ALBERTO CORRALES Date: 08/ 18 / 98
Person who received the bids: A. CORRALES Received at: CITY CLERK'S OFFICE, CITY HALL
Construction Estimate = $ 38,500.00 Time: 10:00 A.M.
BIDDER
11EISS,000LRICH SO.ENT.INC.
MET CONSTRUCTION INC.
ADDRESS
1431 S.a 30 AVE.
DEERFIELD BEACH, FL. 33442
406 NW 54 ST.
MIAMI. FL 33127
BID BOND AMOUNT
B.B. 5%
B.B. VOUCHER
IRREGULARITIES
H
MINORITY OWNED
NO
YES
ITEM No.
DESCRIPTION
UNIT
PRICE
TOTAL
UNIT
PRICE
TOTAL
UNIT
PRICE
TOTAL
UNIT
PRICE
TOTAL
BASE BID TOTAL OF ITEMS 1 THRU 2
842,000.00
$70.000.00
1
FOR FURNISHING OF ALL LABOR, MATERIALS,
EQUIPMENT AND SUPERVISION NECESSARY
TO REMOVE THE EXISTING ROOFING MATERIALS,
AND INSTALL A SINGLE -PLY MEMBRANE, AS
SHOWN ON THE SPECIFICATIONS.
$39,000.00
$67,000.00
2
PROVISIONS FOR SPECIAL ITEMS
$3,000.00
$3,000.00
' IRREGULARITIES LEGEND IT HAS BEEN DETERMINED BY THE DEPARTMENT OF PUBLIC WORKS THAT
A - No Power -of -Attorney THE LOWEST RESPONSIBLE AND RESPONSIVE BID IS FROM WEISS & WOOLRICH
B - No Affidavit as to Capital & Surplus of Bonding Company SOUTHERN ENTERPRISES INC. FOR THE TOTAL AMOUNT OF $42.000.00
C - Corrected Extensions
D - Proposal Unsigned or Improperly Signed or no Corporate Seel If the above contractor is not the lowest bidder explain:
E - Incomplete Extensions P
F - Non -responsive bid _
G - Improper Bid Bond y --_ _ _ -_ _ _ - -- - -
-------- -------------------------------
H - Corrected Bid - _'= ------------------
I - No First Source Hiring Compliance Statement _�SfrTf ---------------------------------------------------
J - No Minority Compliance Statement
---------------------------- --------------------------------- - o Copy of Certificate of Competency 1 OF 1
L - LOCK OF REQUESTED EXPERIENCE ------------ ------------ ----------------------------------------
TO Donald H. Warshaw
City Manager
FROM : James J. Kay, irector%'
Public Works Department
CiTY OF MIAMI. FLORIDA
INTER -OFFICE MEMORANDUM ^" OICE
FF
QIn 4Z7D -1) AM 11: 49
DATE AUgUSf-tL499$- PL
SUWECT : Coconut Grove
Convention Center
Office Roof Replacement
(B-6304)
REFERENCES:
ENCLOSURES:
The "emergency" memo prepared by the Department of Conferences, Conventions
and Public Facilities (CCPF) for replacement of the Coconut Grove Convention
Center office roof, and approved by you on July 10, 1998, requested authorization
to proceed to obtain informal bids on an emergency basis. Although CCPF'S intent
was to have the roof replaced as soon as possible, they did not include the award
of a construction contract in their emergency request.
The Department of Public Works received bids on a formal basis since the project
was ready to be advertised for bid when the "Emergency" memo was received.
Although it may be a technicality, we would like to formally request your approval
to award a .contract on an emergency basis and to submit a resolution for City
Commission action at the earliest possible date to ratify and confirm your action in
aw rding this contract on an emergency basis.
,ISM/JJK/ I% nm
c: Raul Martinez, Interim Assistant City Manager
Christina P. Abrams, Director, CCPF
Allan Poms, C ief Architect, Public Works
OPPROVE 111 -- DISAPPROVED
Donald H. Warshaw
ity Manager
Date 4,1i 9
Donald H. Warshaw
City Manager
CGCCroofRePI.dOC
08-10S6
CITY OF MIAMI. FLORIDA
INTK�FEV MEMORANDUM CITY MANAGERS OFFICE
TO: Donald H. Warshaw 98 JUL 20 AM 7= 54 DATE: July 6 1998 FILE :-
City Manager 01 * OF PUBLIC WRIS
THE CITY OF MIAMI. FLA. su84Ec Coconut Grove Convention Center
FROM: Christina P. Abrams, Director
Conferences, Conventions & Public Facilities
Roof Replacement
L
REFERENCES:
ENCLOSURES:
This memorandum serves to request your authorization to proceed on an emergency basis to obtain
informal bids for the replacement of the Coconut Grove Convention Center office roof.
Attached is a memorandum dated June 24, 1998 from Allan Poms, and other related memoranda
referring to the roof replacement of the offices at the Coconut Grove Convention Center. It has
become a serious situation as the roof has deteriorated with numerous interior leaks, and needs
immediate attention. Due to the serious water intrusion, Greg Wright, the Convention Center
Manager, has had to vacate his office. It is not only an inconvenience for staff, but an
embarrassment to expose clients to offices in such deplorable condition. Funding is available for
this roof replacement from CIP Project 415003.
Please indicate your preference by signing below.
Approve -
Donald H. Warshaw, City Zger
Date: /10 (tre
Attachments
CPA:TB:yp
cc: Greg Wright
Disapproved:
Donald H. Warshaw, City Manager
98-103'16