HomeMy WebLinkAboutItem #61 - Discussion ItemTO :
FROM
5A
CITY OF MIAMI, FLORIDA DISTRICT
INTER -OFFICE MEMORANDUM COMMISSIONER TEELE
The Honorable Mayor and Members
of the City Commission
r
Don ld H. Warshaw
City Manager
DATE : JUL 5 1999 FILE :
SUBJECTReport Update on
Hadley Park Community Center
REFERENCES:
ENCLOSURES:
As requested by the Miami City Commission at its June 22, 1999
meeting, we are please to provide the following report update on
the Hadley Park Community Center Project,
On June 25, 1999, a fully executed agreement between the City of
Miami and the State of Florida was sent to the Department of
Management Services (DMS) for the Hadley Park Community Center
Project. Attached please find a copy of that transmittal.
DMS will now conduct a three to four week process to select the
Construction Manager at Risk. To this end, an organizational
meeting with DMS Project Director Ralph Martinez and City staff
has been scheduled for July 1, 1999 at the Miami Riverside
Center. The first priority at this meeting will be to select a
Construction Manager at Risk for the project.
Thaddeus Cohen, the project architect, is approximately 500
complete with the architectural construction plans and bid
documents. We expect commencement of construction in October,
1999.
DHW/RM/X1 /gc
P I+
�s�ss�ay.
kTitv of fflimni
TAMES J. KAY, P.E.
Director
June 25, 1999
State of Florida
Department of Management Services
Building Construction
Building 4030, Suite 315
4050 Esplanade Way
Tallahassee, FL 32399.0950
Attention: H. R. Hough
Contracts Administrator
RE: COM-98064000
CITY OF MIAMI, PUBLIC WORKS DEPARTMENT
CONSTRUCTION MANAGEMENT SERVICES FOR THE
DESIGN AND CONSTRUCTION OF A CULTURAL CENTER
UNDER A "CONSTRUCTION MANAGER AT RISK" PROCESS,
MIAMI, FLORIDA
DOCUMENT: AGREEMENT BETWEEN THE CITY OF MIAMI AND
THE STATE OF FLORIDA DEPARTMENT OF MANAGEMENT
SERVICES BUILDING CONSTRUCTION (BC)
Gentlemen:
DONALD H. WARSHAW
City Manager
Enclosed is an original copy of the above referenced document which has been fully
executed by the City of Miami and approved by the Financial Oversight Board. we are
now ready to proceed with the Hadley Park Community Center project under the
"Construction Manager at Risk" process.
The City staff is anxious to begin the construction management phase of this project
since the architect is nearing completion of the construction plans. Please contact Allan I.
Pours, A.I.A., Chief Architect, at 305-416-1245 and Maria Perez, (305-416-1314) Support
Services Coordinator, Department of Parks and Recreation. We are looking forward to
working with your Building Construction staff.
Sincerely,
James J. Kay, E.
Director
c: Raul Martinez, Assistant City Manager
Albert Ruder, Director, Parks and Recreation
Allan 1. Poms, Chief Architect
Maria M. Perez, Support Services Coordinator
Harold Barrand, Director, BC
Thaddeous Cohen, A.I.A. P L
DEPARTMENT OF PUBLIC WORKS /444 S.W. 2nd Avenue/Miami, Florida 33130/(305)416.1200/Fax� kisf,9,
Mailing Address: P.O. Box 330708 Mlami, Florida 33233-0708
CON'i t ACT REVIEW AND AA^LYSIS FORM
Directions: Please Attach supporting documents. All sections must be completed; excluding "CRC Comments %
Date:
DEPARTMENT/DIVISION: Public Works
CONTACT PERSON / CONTACT NUMBER: Tony Pratt 416-2131
CONTRACTING ENTITY: State of Florida Deipartment of Management Services
RESOLUTiONNUMBER. 99 —291 BID:
BUDGETARY INFORMATION: Are funds budgeted? YES �
TOTAL DOLLAR AMOUNT. S 57, 636. ❑ EXPENSESOURCE OF FUNDS: Safe Neighborhood ACCOUNTCODE(S)
Parks Bond
If grant funded, is there a City match requirement? YES ❑ NO 13
Are matched funds Budgeted? YES ❑ NO ❑ Account Code(s):
( If AppUcable )
NO ® Ifyea,
❑ REVENUE
3313A/.589305.6.270
AMOUNT: $57,636.00
TERMS OF CONTRACT: (To be filled out by Purchasing Department) t' �0v% (.%li (0� q r►
EffectiveDw— evon execution of aereement. 'I
Esala nClause,ifmy. _ NIA
C0n1rZCtM0d(s):From execution to Protect completion,
Payment terms: ..12_Cglita1..pa=v nts efS4.Sb3.
Penahies, (if any), for tawiaatilm. N/A
If grant fimded, list rearWons acquirements, if applicable:
SUMMARY/DESCRIPTION OF CONTRACT OR AGi til ANT
T
Is this an extrusion? YES ❑ NO ® Reason for Extamim-
If YES, actual ezpendrw res in previous contnwt Year
Summary/Description of Contract or Agreement:
JUSTIFICATION FOR CONTRACT OR AGREEMENT
(Mdode why it is wed. oomequetroa If not aadwind or approved and time one:trah tf aaq.)
This acreement is necessary to oversee the design and construction of the Hadley
Park Community Center, A project of the CouaKy Safe Neighborhogd Parks Bond Program,
METHOD OF PIIRZZASE (If applicable)
® Telephone quom, p Sin0c Pumhw
p Women Quota G Sbw-Tam Convaet
p Ncjodated Purd►are 0 Law ( Type: )
p Sole Sours (include documentation) C3 Tam of Contract
Bid Waives WL,4e doaursattadon) i
(3 Forma! BldTroposal (include bid taiwlation/proposal rankinS)
PREVIOUS AWARDS OF BID (1F APPLICA•BLE)
From most recent: I)
Approval:
CRC COWKENTS:
Approval:
Fenancia
r>r7•aarin.'..�.� s
w
STATE OF FLORIDA
DEPARTMENT OF MANAGEMENT SERVICES
BUILDING CONSTRUCTION (BC)
BUILDING 4030. SUITE 315
4050 ESPLANADE WAY
TALLAHASSEE. FLORIDA 32399-0950
FORM OF AGREEMENT BETWEEN
CLIENT AND AGENT
BC PROJECT NUMBER: COM-98064000
PROJECT NAME AND LOCATION: CITY OF MIAMI. PUBLIC WORKS DEPARTMENT.
DESIGN AND CONSTRUCTION OF A COMMUNITY
CENTER AT HADLEY PARK, UNDER A
CONSTRUCTION MANAGER AT RISK PROCESS,
MIAMI. FLORIDA
CLIENT: CITY OF MIAMI
PUBLIC WORKS DEPARTMENT
RIVERSIDE CENTER, 8TH FLOOR
444 SW 2ND AVENUE
MIAMI, FLORIDA 33130
cityofmaimica
Jeb Bush
Governor
Tom McGurk
Secretary
AGREEMENT FOR SERVICES
THIS AGREEMENT
made this _ day of in the year Nineteen Hundred and Ninety Nine
BY AND BETWEEN BUILDING CONSTRUCTION (BC). DEPARTMENT OF MANAGEMENT SERVICES.
STATE OF FLORIDA. hereinafter called the AGENT or BC, and
CITY OF MIAMI
PUBLIC WORKS DEPARTMENT
RIVERSIDE CENTER. 8TH FLOOR
444 SW 2ND AVENUE
MIAMI. FLORIDA 33130
herinafter called the CLIENT or OWNER.
WITNESSETH, that whereas the CLIENT wishes to retain the services of BC, as permitted by Chapter 255.31.
Florida Statutes, for providing certain program management services for the Project described on the cover page of
this Agreement.
NOW THEREFORE. BC and the CLIENT, for the considerations hereinafter set forth. agree as follows:
Article 1. BC agrees to furnish those Program Management Services described in the attached Exhibit 1, which
Exhibit I by reference and attachment hereto forms a part of this Agreement.
Article 2. The Project Budget is as shown in the attached Exhibit II. which Exhibit II by reference and attachment
hereto forms a part of this Agreement.
Article 3. The proposed schedule is as shown in the attached Exhibit III, which Exhibit III by reference and
attachment hereto forms a pan of this Agreement.
Article 4. BC is authorized and requested to enter into agreement or assignment with architects. engineers,
contractors, etc., using BC forms and procedures, for the design, bidding and construction of those parts of the
Project. The CLIENT understands and agrees that those agreements will designate BC as the AGENT for the
OWNER and will contain a provision substantially as follows:
The entity that will occupy, use and own the Project upon substantial completion is City of Miami. Parks
and Recreation Department. Miami. Florida. The funds with which the compensation of the architects,
engineers. contractors, etc., will be paid are under the control of City of Miami. Parks and Recreation and
Public Works Departments, Miami, Florida. Payments under this contract, as prescribed hereinabove, will
be made by either City of Miami, Public Works Department or the Parks and Recreation Department,
Miami. Florida, based on approval of each payment by BC, Department of Management Services. State of
Florida.
CLIENT agrees that, although it will not execute those agreements, the agreements shall be deemed to be the
agreements of the CLIENT in view of the fact that the funds are under the control of the CLIENT and BC will not
have responsibility to make payments on the agreements.
Article 5. CLIENT agrees to designate a representative for the Project to be solely responsible for all CLIENT
actions under this agreement, and who will receive, review and respond in a timely manner to all questions and
requests from BC; and to pay, within thirty (30) calendar days, all invoices approved by BC and transmitted to the
CLIENT for payment, not exceeding the portions of the budget shown on the attached Exhibit II which have been
activated in writing by a letter from the CLIENT's representative to BC.
A
Article 6. BC does not guarantee the Project can be completed within the budget shown in the attached
Exhibit II, but does agree not to commit funds in excess of this budget without mutual agreement and an
Amendment to this agreement authorizing such increase.
Article 7. BC's administrative fees for the various program management services are based on services as
shown in Exhibit I and shall be as follows:
FIFTY SEVEN THOUSAND, SIX HUNDRED THIRTY SIX HUNDRED THIRTY SIX DOLLARS ($57,636.00)
If the Projecq Budget is increased in excess of $250,000.00 or if the Construction Schedule exceeds 12
months then BC fee shall be increased by 2.2% of the revised budget in excess of $2,650,000.00. If the
Construction Schedule can be reduced BC's fee shall be reduced by $4,803.00 per month or a prorated
thereof. If the Construction extends beyond 12 months due to no fault of BC, the fee will be $4.803.00 per
month or a prorated portion thereof.
Article 8. BC's administrative fees prescribed in Article 7 herein above, will be invoiced once for the total
amount due and payments are to be made in 12 consecutive monthly payments against the invoice based on
an 12 month final completion date.
$57,636.00 � 12 months = $4,803.00 12 Equal Monthly Payments of $4,803.00
Article 9. Additional Services will be performed for a separate fee to be negotiated and authorized later.
Such services may include, but are not IL-nited to the following:
Special Board meetings or workshops
Article 10. This Agreement may be terminated by either party upon seven (7) days' notice by mutual
agreement, or should one party fail substantially to perform in accordance with its terms through no fault of
the other. In case of termination, BC, its Contractors and Architect -.Engineer's shall be paid for services
performed up to the date of termination and any reasonable additional costs that BC, it's Contractors and
Architect -Engineers may incur as a result of terminating this agreement.
Article 11. Insurance
The BC covenants and agrees that all contracts between BC and other third -parties regarding the
performance of any work at the Project shall contain, as a minimum, the following:
a) an indemnification and hold harmless agreement to in favor of the City of Miami from all
claims arising out of the performance any work on the property.
b) a requirement that the City of Miami be named additional insured in all liability policies.
BC agrees that its contract with the CM will contain a requirement that all of the CM's subcontracts
relating to this project contain the same indemnification language as (a) & (b) above.
BC further agrees to provide to the City with a copy of all such agreements and the contractors insurance
policy prior to the commencement of any work under any such contract.
``� I�st�.i��rt�rs�•
IN \\'ITNESS %WHEREOF. Inc parties hereto have executed this Agreement we day and )ear fir*zt Vrtttcn aNAN-C.
CLIENT
Attest:
By:—L/ L
jWa�t'er J. Fo an, City Clerk
Approved as to Insurance Requirements:
By
//�)tc f i .
`V r
Mario Soldeyilla. Risk Management
AGENT
As Witnessed:
By:/ i
v'
CITY OF MIAMI. A MUNICIPAL
CORPORATION OF THE STATE
OF FLORIDA
nald . War!, City Manage
i
Approved as to Fob Correcitless:
rr
BUILDING CONSTRUCTION.
DEPARTMENT OF MANAGEMENT
SERVICES.
STATE OF FLORIDA
Approved:
�/-
By:
H.R. Hough
Contracts Administrator
Approved As To Form And Legality:
By: &�--L 446—//
Office of General Counsel,
Department of Management Services
State of Florida
�ti
EXHIBIT I
SCOPE OF SERVICES
Building Construction. Department of Management Services. State of Florida. hereinafter referred to a. "BC".
proposes to provide the following program management services for the projects identified on the face r1 this
Agreement:
1. A/E's Design Development Phase Services
BC WILL:
Accept Assignment Of A/E's Contract With The City Of Maimi. Public Works Department
Provide Direction/Consultation To The A/E As Required Regarding Scope. Additional
Services. Procedures . etc. y
Provide Information To The A/E Regarding Permitting Agencies and Codes to Use
Provide Budgetary Direction To The A/E
Participate In Value Engineering Analysis To Provide The Best Project Within Budget
Review Plans For Architectural. Mechanical. Electrical And Civil And Provide
Comments To The A/E
Reviews A/E Responses And/Or Revisions Due To DBC (And Other Reviewing Agencies) Comments
Monitor The Schedule For Submittals And Establish Dates For Reviews
Reviews A/E Requests For Additional Services For Scope. Completeness. Fairness
Issue A/E Additional Services Authorizations Agreed Upon
Receive. Review And Approve A/E Invoices For Services Rendered Versus Contract
Conditions
Process A/E Invoices To Proper Accounting Office For Vouchering
Review And Analyze Cost Estimates
Review Specifications
Assure Meetings .Are Documented And Minutes Distributed To All Parties
Assure All Decisions Required For That Particular Design Phase Are Mace
Issue Approval To A/E To Proceed Into Next Phase
THE FOLLOWING WILL BE PROVIDED BY THE A/E UNDER CONTRACT TO BC
Conferences With Client & Others
Site - Informational Data
Master Plan
Environmental Considerations
Grading & Site Development
Site Construction
Roads. Walks, Paths & Parking
Utilitv Services
Fencing
Landscaping
Lateral & Transverse Site Sections
Special Site Considerations
Buildings - Architectural:
Floor Plans
Area Recap
Elevations
Building Sections
Typical Wall Sections
Finish & Equipment Schedules
Color Pallet & Schedule
Code Classifications
Complex Area Plans
List Of Safety Equipment
Design Concept Sketch
1\lateriak List
Other Information
Buildings - Structural:
- Describe Foundation Conditions
Describe Structure Selected
Preliminan, Framing Plan
Describe Roof Structure
Structural Building Sections
Identify Building Loads
Design Calculations cS Criteria
Special Conditions
Buildings - HVAC:
Single Line Layout With Equipment
Sections Showing Equipment
Fleet Forms -
Describe Auto Management System
Describe Criteria For Heating System
Describe Ventilation System
Describe AC Criteria & System
Describe Evaporative Cooling System
Buildings - Refrigeration:
Areas To Be Refrigerated
Outside Design Temperatures
Type Refrigeration Equipment
Type/Thickness Insulation
Buildings - Electrical:
Describe Electrical Service Entrance
Describe Electrical Characteristics
Identify Panel Locations
Describe Wiring Systems
Describe Conductors
Locate Lights. Outlets & Switches
Describe Standards Of Design
Describe Short -Circuit Duty
Describe Emergency Electrical Systems
Coordinate Building & Site Electrical
Other
Buildings - Communication:
Describe Systems
Describe Materials
Describe Locations
Describe Radio Paths
Describe Antenna Requirements
Describe Antenna Transmission
Describe Bonding & Grounding
Describe Cable/Radio Links
Describe Test Equipment
Describe Equipment Arrangement
Describe Wiring/Cable Requirements
Describe Lighting/Power Requirements
Describe AC Requirements
Describe Interference/Clearance
Buildings - Plumbing:
Preliminary Layout Of Lines
Preliminary Plan Locations
Preliminary Section With Risers
Identify Number Of Fixtures
00ft ,
,>S"e. -
Identify 1N ater Pressure
Identify Hot Water Sy>tem
Other
Buildings - Fire Protection:
Identify Hydrant
Identify Riser/Hose Cabinets
Identify Sprinkler Criteria
Insurance Design Criteria
Sprinkler Head Layout
Buildings - Special Equipment:
Kitchen Equipment
Auditorium Seatine
Stage Curtain And Equipment
Gym Layout And Equipment
Window Coverings
Hospital Equipment
Lawn Sprinkler Equipment
Vacuum Cleaning Svstems
Material Handling Equipment
Telephone Systems
Other Systems
Checklist
Bid Packages/Sequences:Base Bid & Alternates
Probable Construction cost
Area Analysis
Telephone Site Plan
Distribution Of Review Packages
BC Review
A/E's Response To Review Comments
3 A/E's Construction Documents Phase Services
BC WILL:
Provide Direction/Consultation To The A/E As Required Regarding Scope, Additional
Services, Procedures , etc.
Provide Information To The A/E Regarding Permitting Agencies and Codes to Use
Provide Budgetary Direction To The A/E
Participate In Value Engineering Analysis To Provide The Best Project Within Budget
Review Plans For Architectural, Mechanical. Electrical And Civil And Provide Comments To
The A/E
Reviews A/E Responses And/Or Revisions Due To BC (And Other Reviewing Agencies) Comments
Monitor The Schedule For Submittals And Establish Dates For Reviews
Reviews A/E Requests For Additional Services For Scope, Completeness, Fairness
Issue A/E Additional Services Authorizations Agreed Upon
Receive, Review And Approve A/E Invoices For Services Rendered Versus Contract Conditions
Process A/E Invoices To Proper Accounting Office For Voucherino
Review And Analyze Cost Estimates
Review Specifications
Assure Meetings Are Documented And Minutes Distributed To All Parties
Assure All Decisions Required For That Particular Design Phase Are Made
Issue Approval To A/E To Proceed Into Next Phase
THE FOLLOWING WILL BE PROVIDED BY THE A/E UNDER CONTRACT TO BC
Conferences With CLIENT
5017c Documents Review
Non -Technical Specifications
Fleet/Solar Energy
Codes Certification
"� L JLL
Check List
Cost Estimates
Area Analysis
Color Schedules
Handicapped Check List
Draw•in2s
Technical Specifications
Bid Packaees
Alternates
Mechanical Test And Balance
1009c Documents Review
100% Review Response
3. A/E's Bidding Phase Services (If Applicable)
BC WILL.
Prepare Sample Advertisement For A/E To Use In Newspapers
Issue State MBE Directon, To The A/E To Be Made Available To Contractors (As Required
To Meet Project Goals)
Monitor Addenda For Scope And Clarity
Participate In Bid Openings
Review Contracts Financial Qualifications And Experience
Make Recommendations For Bid Award
THE FOLLOWING WILL BE PROVIDED BY THE A/E UNDER CONTRACT TO BC
Prepare Camera Ready Cop), Of Documents For Each Bid
Packaee
Prepare S Issue Addenda
Attend Bid Openings
Award Recommendations
4. A/E's Construction Phase Services
BC WILL:
Prepare And Issue The Notice To Proceed
Participate With The A/E And Contractor In The Initial Construction Conference
Review The Contractor's Schedule For The Project
Participate In All Monthly (Or Bi-Weekly) Team Meetings
Assure All Team Meetings Are Documented And Minutes Sent To All Parties
Review Contractors List Of Subcontractors
Review Monthly RFI, ASI, Submittal, Shop Drawings And Other Logs For Timeliness
Review Contractor's Progress Against The Schedule On A Monthly (Or Bi-Weekly) Basis
Analyze Change Order Proposals For Scope, Need, Completeness. Fairness
Recommend Change Orders As Required
Review Contractor's Pay Requests
Process Pay Requests To The Appropriate Accounting Office For Voucherina
Participate In Monthly Inspections With The A/E
Participate In Substantial Completion In.: -.rctions
Participate In Final Completion Inspections
Review And Sign Affidavits Of Completion
THE FOLLOWING WILL BE PROVIDED BY THE A/E UNDER CONTRACT TO BC
Initial Construction, Conferences
Project Sign Design
Monthly Construction Conferences
Review Contractor's Progress Schedule
Review Contractor's List Of Subcontractors
Review Contractor's Shop Drawings
Transmit Payroll Records Required By Federal Grants
,> $i VArfi44;--.
"...,
T,
Review As -Built Dra..tngs
Clarification Documents
A1onthly Status Report
Site Visits And Reports
Monthly Contractor Payment Reviews
Review Testing Invoices
Change Orders
Claim Reviews And Correspondence
Substantial Completion Inspection
Final Completion Punchlist
Final Inspection
Review Contractor's Affidavits Of Completion
Review Contractor's Guarantees And Operating Manuals
Review Contractor's As -Built Drawings
5. Contractor Selection
BC WILL:
Establish Contractor Selection Team Consisting Of BC, A/E &
CLIENT Personnel
Advertise For Qualified Contractors
Prepare Project Scope Information For Contractors
Answer Contractor's Questions
Verify Contractor Prequalification Criteria
County & State Licensure/Certification/Corporation
Analyze Previous Experience On Similar Projects
Analyze Management Staff & Experience
Analyze Site Management Capability
Analyze Present Workload
Schedule/Arrange Contractor Selection Meetings
Conduct Preliminary Selections, Reducing Applicants To 5
Contractors
Publish Shortlist Results Of Contractor Selections
Debrief Unsuccessful Contractors
Brief Successful Contractors
Conduct Interviews With Remaining 5 Contractors
Finalize Selection. Reducing To 3 Contractors In Order Of
Preference
Debrief Ranked Contractors
6. Contractor Fee Negotiations
BC WILL:
Establish Contractor'Negotiation Team Consisting Of BC,
A/E & CLIENT Personnel
Prepare & Publish Detailed Scope For Contractors
Notify Number I Contractor Of Negotiation & Proposal
Requirements
Answer Number I Contractor's Questions
Receive & Analyze Proposal From Number 1 Contractor
Conduct Pre -Negotiation Conference With Negotiation Team
Conduct Negotiations of Contractor's Fee With Number 1 Contractor
Establish On -Site Design Personnel Requirements
Establish Off -Site Design Personnel Requirements
Establish On -Site Construction Personnel Requirements
Establish Off -Site Construction Personnel Requirements
Establish General Conditions Requirements
Establish Design & Construction Phase Fee
Establish Overhead & Profit Fee
Establish vreliminary Schedule Requirements
Establish Construction Team. Consisttnc Of BC. CLIENT.
A/E & Contractor Personnel
Coordinate With CLIENT
Distribute Results Of Negotiation
Obtain CLIEtiT Approval
7. Contractor Contract Preparation/Execution
BC WILL:
Prepare Contract On BC's Form For Contractor & BC
Execution
Prepare Performance Bond On BC's Form In Budget Amount
Prepare Labor & Material Payment Bond On BC's Form In
Budget Amount
Prepare Certificate Of Insurance On BC's Form
Prepare Assignment Of Contractor's Antitrust Rights To CLIENT
On BC's Form
Process Contract Documents To Contractor For Execution
Receive Executed Documents Back From Contractor &
Thoroughly Check For Proper Execution
Execute Documents On Behalf Of CLIENT
Give Contractor Notice -To -Proceed With Design Phase Services
S. Contractor's Design Phase Services
BC WILL:
Participate With The A/E And Contractor/CM In Plan Reviews At Each Submittal Phase
Participate With The A/E And Contractor/CM In Value Engineering Alternative
Design/Construction Approaches
Review All Contractor/CM Estimates
Review Contractor/CM GMP With The Team And Recommend For Contracting
Explore Tax Savings And Implement Procedures As Necessary
THE FOLLOWING WILL BE PROVIDED BY THE CONTRACTOR/CM UNDER CONTRACT TO
BC (WITHOUT ASSUMING DESIGN RESPONSIBILITIES)
Distribute Document Package
Schedule Familiarization Meeting
Conduct Familiarization Meeting
Manage Requests For Information
Pricing & Value Engineering (VE)
Review & VE Site Civil
Review & VE Mechanical -Electrical Systems
Review & VE Structural Systems
Review & VE Roof & Exterior
Review & VE ADA Compliance
Review & VE Detail Coordination
Evaluate Construction Phasing
Evaluate Constructability
Propose Guaranteed Maximum Price (GMP)
Negotiate Final GMP & Conditions
Document Final GMP & Conditions
Review Final GMP & Conditions With CLIENT Team
Obtain CLIENT Team Approval Of Final GMP & Conditions
Amend Contractor's Contract To Reflect Final GMP/Conditions
Prepare GMP Amendment To Construction Contract
Process GMP Amendment To Contractor For Execution
Receive Executed Amendment Back From Contractor &
Thoroughly Check For Proper Execution
9
Execute Gn,r' Amendment On Behalf Of CLIENT
Process Executed GRIP Amendment To Contractor
9. Contractor's Construction Phase Services
BC WILL:
Prepare And Issue The Notice -To -Proceed
Participate With The A/E And Contractor In The Initial Construction Conference
Review The Contractor's Schedule For The Project
Participate In All Monthly (Or Bi-Weekly) Team Meetings
Assure All Team Meetings Are Documented And Minutes Sent To All Parties
Review Contractor's List Of Subcontractors
Review Monthly RFI. ASI. Submittal. Shop Drawings And Other Loes For Timeliness
Review Contractor's Progress Against The Schedule On A Monthly (Or Bi-Weekly) Basis
Analyze Change Order Proposals For Scope. Need. Completeness, Fairness
Recommend Chance Orders As Required
Review Contractor's Pay Requests
Process Pay Requests To The Appropriate Accounting Office For Vouchering
Participate In Monthly Inspections With The A/E
Participate In Substantial Completion Inspections
Participate In Final Completion Inspections
Review And Sign Affidavits Of Completion
THE FOLLOWING WILL BE PROVIDED BY THE CONTRACTOR/CM UNDER CONTRACT TO
BC (WITHOUT ASSUMING DESIGN RESPONSIBILITIES)
Coordinate Contractor's Project Promotion & Advertisement
Contact Qualified Sub -Contractors
Promote Through Associations & Exchanges
Promote MBE participation To Make Good Faith Effort
Toward Meeting District Board Of Trustees Requirements
Use BC &. CLIENT Databases Of Interested Contractors
BC & CLIENT To Participate In Pre -Bid Meetings & Bid
Openings
Coordinate Contractor's Review Of 100% Construction
Documents
Give Contractor Notice -To -Proceed With Construction
Coordinate Contractor's Project Information Management
Key Personnel Contacts
Budget & Financial Data
Project Construction Scheduling
Construction Progress Conference Scheduling
Interface With Construction Management Systems
Initial Team Construction Conference
Maintain Constructive Agenda
Document Potential Areas Of Concern
Develop Subcontractor Coordination Plan
Review Construction Critical Path
Confirm Communications Network
Weekly Team Meetings
Monthly Team Meetings
Prepare For Meetings
Attend Meetings
Prepare Monthly Report
Review Submittal Schedule
Identify Long -Lead Submittals
Coordinate Review Periods With Construction Schedule
Review Budget Status
Review Value Analysis Reports
10
000>stwzo�
fl
Perform Quality Control Observations
Review Construction Schedule
Review Change Proposals. Reviews And Implementation Are
To Be By The Construction Team On Changes To The G11P
That Are Less Than S I00.000. Those Changes Equal To
Or Greater Than S100.000 Will Require CLIENT Approval,
Review MBE Participation Reports
Review Testing Reports
Review Building Code Inspection Reports
Review Requests For Payment & Transmit To CLIENT For Review
& Pavment
Establish Transition Team
Monitor As -Built Development
Substantial Completion Inspection
Review A/E Certifications
Expedite & Verify Punchlist Corrections
Review Warranties & Submittals
Final Inspection & DOE Certification
10. Occupancy -Services (Additional Service to Owner)
BC WILL:
Assure Staff Training Occurs For Equipment
THE FOLLOWING WILL BE PROVIDED BY THE CONTRACTOR/CM UNDER CONTRACT TO BC
(WITHOUT ASSUMING DESIGN RESPONSIBILITIES)
Review Occupancy Requirements
Coordinate Maintenance & Operational Training
Review Systems Testing & Certifications
EX14101T III PnOPOSED SCHEDULE. CI1 Y OF MIAMI
Took Name
Duration
Start
Finish
--- 1999
2000
_
M _A _M J J A r S��_N�D
J 1 F M A M d LJ
OMS Selected by Board
0 days
7 days
Tue 3123199
Tue 3123/99
Tue 312 V99
Mon 3/29/99
ri
r:
' f
f. 1
L t
"1141
-- !� -- — 3/24
WE Contracting Phase
A/E Assignment Preperalion/Execulion
7 days
Tue 3/23/99
Mon 3/29/99
Tue 7127/99
A/E Deslgn Phase
120 days
Tue 3130/99
A/E Sile Development Permitting
90 days
_ Tuo 3130/99
Sun 6/27/99
Fri 5/20/99
A/E Design Development Phase Services
60 days
Tua 3/30199
A/E Construction Documents Phase Services
60 days
—Sat 5/29/99
Tue 7/27/99
Thu 3/23100
A/E Construction Phase Services
240 days
YJed 7/28/99
A/E Construction Administration & Silo Visits
240 days
Wed 7/28/99
Thu 3/23/00
Fri 5/14199
CM Selection Phase
52 days
Wed 3/24/99
Advertise for Construction Manager
30 days
Wed 3/24/99
Thu 4122199
Selection Team Reviews Proposals Individually
5 days
Fri 4/23/99
Tue 4127199
Selection Team Meets, Produces Short List
1 day
Wed 028199
Wed 4I28199
Short Listed C/M Prepare for Oral Presentation
14 days
Thu 4129/99
Wed 5112/99
Oral Presentations & Grading by Team
1 day
Thu 5113/99
Thu 5/13/D9
Notification and Advertisement of the Results
1 day
Fri 5114/99
Fri 5/14199
CM Contracting Phase
28 days
Set 5/1s/99
Fri 6/11/99
CM Negotiations
14 days
Sal 5115/99
Fri 5/28/99
CM Contract PreparatiorVExecution
14 days
Sal 5/29/99
Fri 6/11/99
CM Design Phase
90 days
Sat 6/12/99
Thu 9/9/99
Design Development Estimate
30 days
Sat 6/12/99
Sun 7111/99
Construction Documents/GMP Estimate
60 days
Mon 7/12/99
Thu 9/9/99
CM Construction Phase Services
240 days
Wed 7/28/99
Fri 3/24/00
Construction
240 days
Wed 7/28/99
Thu 3/23/00
Substantial Completion
30 days
Wed 2/23/00
Thu 3/23100
Final
0 days
Fri 3/24/00
-- Fri 3124/00
City of Miami
ru 4129199
Task
Progress
Milestone .
Summary
Rolled Up Task fe,fi;
Rolled Up Milestone Q
Rolled Up progress
Exlernal Tasks
Project Summary
Split
dolled Up Split