City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Public Safety
Proposed Proiect:
Homeland Defense Preparedness Initiative (Police)
Is this item expressly identified in the Proposed G.O. Bond Issue List of Proiects?
Yes
Total Amounted Allocated:
$11 Million (1/2 to Police $5.5 Million)
PROJECT CRITIERA
Projected Time Line: The Miami Police Department has submitted a list of items suggested for purchase within the next
year which would further enhance the Department's ability to prepare, react and respond in cases of crisis be it local or
international threats of harm/violence. (See Attached List).
Estimated Cost (Expenditure Required Per Year):
Year One: $2,676,800
Year One: 323,200
Year One Total: 3,000,000
Remaining Balance: 2,500,000
Will Land Acquisition Be Required, If so, how much?
N/A
Job Creation Potential (First Source Hiring Agreement):
N/A
Economic Development Impact:
Indirectly
Tourism Impact:
Indirectly
Purchase of Identified Items
Emergency Contingency Fund
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): As a result of the proposed purchases, the estimated impact on the City's General Revenue Fund would be
$307,800 to cover the cost for maintenance and repair of the proposed purchased items.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Communications Interoperability and Information Sharing Technologies (AGILE R&D) Program, US DoJ
Port Security Grants Program, US DoT
Using Service and Volunteers to Support Homeland Security, US Corp for National and Community Service
Critical Infrastructure Protection Grants Program, US DoC
Pre -Disaster Mitigation Program, FEMA
First Responder Initiative Grant Program, FEMA
Targeted Capacity Expansion Grants to Address Mental Health Service Needs of Public Safety Workers Responding
to Terrorist Attacks, US DHHS SAMHSA
Shelter Retrofit Report, (Part A) Proposals, FL DCommA
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
City of Miami Bond Program ,_..,r
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Public Safety
Proposed Project:
Homeland Defense Preparedness Initiative (FIRE)
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$11 Million (112 to Fire $5.5 Million)
PROJECT CRITIERA
Projected Time Line: The Miami Fire Department has submitted a list of items suggested for purchase within the next year
which would further enhance the Department's ability to prepare, react and respond in cases of crisis be it local or
international threats of harm/violence. (See Attached List).
Estimated Cost (Expenditure Required Per Year):
Year One: $1,575,000
Year One: 425,000
Year One Total: 2,000,000
Remaining Balance: 3,500,000
Will Land Acquisition Be Required, If so, how much?
N/A
Job Creation Potential (First Source Hiring Agreement):
N/A
Economic Development Impact:
Indirectly
Tourism Impact:
Indirectly
Purchase of Identified Items
Emergency Contingency Fund
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): None
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Communications Interoperability and Information Sharing Technologies (AGILE R&D) Program, US DoJ
Port Security Grants Program, US DoT
Using Service and Volunteers to Support Homeland Security, US Corp for National and Community Service
Critical Infrastructure Protection Grants Program, US DoC
Pre -Disaster Mitigation Program, FEMA
First Responder Initiative Grant Program, FEMA
Targeted Capacity Expansion Grants to Address Mental Health Service Needs of Public Safety Workers Responding to
Terrorist Attacks, US DHHS SAMHSA
Shelter Retrofit Report, (Part A) Proposals, FL DCommA
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Public Safety
Proposed Project:
Neighborhood Fire Stations and Training Facility -- "In Service Training Center"
Is this item expressly identified in the Proposed G O Bond Issue List of Protects?
Yes
Total Amounted Allocated:
$10 Million (Total Allocation for Fire Stations and Training Facility)
PROJECT CRITIERA
Projected Time Line:
Planning Phase 4 Months
Design/Engineering/Drawings Phase 8 Months
Bid Process 60- 90 Days
Construction Phase 18 — 30 Months
Estimated Cost (Expenditure Required Per Year):
Year One: $300,000 Planning/Design/Engineering/Drawings
Year Two: 600,000 Initial Construction of Facility
Year Three: 600,000 Completion of Construction
Project Total: $1,500,000
Will Land Acquisition Be Required, If so, how much?
No
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the planning and
construction of this facility.
Economic Development Impact:
Indirectly
Tourism Impact:
Indirectly
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?):
None
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Emergency Management Programs Assistance, FL DCA
Assistance to Firefighters Grant Program
Municipal Competitive Grant Program
Florida Emergency Medical Services Matching Grant
Flood Mitigation Assistance, FL DCA
Rapid Emergency Activation/Deployment
USFFA
Critical Infrastructure Protection Grants Program, US DoC
Pre -Disaster Mitigation Program, FEMA
First Responder Initiative Grant Program, FEMA
Targeted Capacity Expansion Grants to Address Mental Health Service Needs of Public Safety Workers Responding
to Terrorist Attacks, US DHHS SAMHSA
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Public Safety
Proposed Project:
Neighborhood Fire Stations and Training Facility -- "Complete Renovation of Fire Station l l/Flagami"
Is this item expressly identified in the Proposed G O Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$10 Million (Total Allocation for Fire Stations and Training Facility)
PROJECT CRITIERA
Projected Time Line:
Planning Phase
Design/Engineering/Drawings Phase
Bid Process
Construction Phase
Estimated Cost (Expenditure Required Per Year):
Year One:
$500,000
Year Two:
750,000
Year Three:
750,000
Project Total:
2,000,000
"Additional Cost:
$60,000
Will Land Acquisition Be Required, If so, how much?
No - Utilizing Current Fire Facility
4 Months
8 Months
60 — 90 Days
18 - 24 Months
Planning/Design/Engineering/Drawings
Initial Construction of Facility
Completion of Construction
Temporary Quarters for Personnel for 2 years
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the planning and
construction of this facility.
Economic Development Impact: Indirectly
Tourism Impact: Indirectly
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): None
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Emergency Management Programs Assistance, FL DCA
Assistance to Firefighters Grant Program
Municipal Competitive Grant Program
Florida Emergency Medical Services Matching Grant
Flood Mitigation Assistance, FL DCA
Rapid Emergency Activation/Deployment
USFFA
Critical Infrastructure Protection Grants Program, US DoC
Pre -Disaster Mitigation Program, FEMA
First Responder Initiative Grant Program, FEMA
Targeted Capacity Expansion Grants to Address Mental Health Service Needs of Public Safety Workers Responding
to Terrorist Attacks, US DHHS SAMHSA
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
City of Miami Bond Program
Summary of Sub -Group Meeting
DraftlWorking Paper
Category:
Public Safety
Proposed Project:
Neighborhood Fire Stations and Training Facility -- "Fire Station 13 — Brand New Facility/Upper East Side"
Is this item expressly identified in the Proposed G O Bond Issue List of Protects?
Yes
Total Amounted Allocated:
$10 Million (Total Allocation for Fire Stations and Training Facility)
PROJECT CRITIERA
Projected Time Line:
Planning Phase 4 Months
Design/Engineering/Drawings Phase 8 Months
Bid Process 60 — 90 Days
Construction Phase 24 - 36 Months
Estimated Cost (Expenditure Required Per Year):
Year One: $500,000 Planning/Design/Engineering/Drawings
Year Two: 1,250,000 Initial Construction of Facility
Year Three: 1,250,000 Completion of Construction
Project Total: 3,000,000
"Additional Cost: $60,000 Temporary quarters for Personnel for 2 years
Will Land Acquisition Be Required, If so, how much?
Yes, unknown at this time. Fire has identified possible sites for the new fire facility.
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the planning and
construction of this facility.
Economic Development Impact: Indirectly
Tourism Impact: Indirectly
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Yes, personnel for the maintenance and upkeep of facility. Amount unknown at this time.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Emergency Management Programs Assistance, FL DCA
Assistance to Firefighters Grant Program
Municipal Competitive Grant Program
Florida Emergency Medical Services Matching Grant
Flood Mitigation Assistance, FL DCA
Rapid Emergency Activation/Deployment
USFFA
Critical Infrastructure Protection Grants Program, US DoC
Pre -Disaster Mitigation Program, FEMA
First Responder Initiative Grant Program, FEMA
Targeted Capacity Expansion Grants to Address Mental Health Service Needs of Public Safety Workers Responding
to Terrorist Attacks, US DHHS SAMHSA
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Public Safety
Proposed Project:
Neighborhood Fire Stations and Training Facility -- "Fire Station 14 — Brand New Facility/Coral Way"
Is this item expressly identified in the Proposed G O Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$10 Million (Total Allocation for Fire Stations and Training Facility)
PROJECT CRITIERA
Projected Time Line:
Planning Phase 4 Months
Design/Engineering/Drawings Phase 8 Months
Bid Process 60 — 90 Days
Construction Phase 24 -36 Months
Estimated Cost (Expenditure Required Per Year):
Year One: $500,000 Planning/Design/Engineering/Drawings
Year Two: 500,000 Initial Construction of Facility
Year Three: 1,500,000 Completion of Construction
Project Total: 2,500,000
"Additional Cost: $60,000 Temporary Quarters for Personnel for 2 years
Will Land Acquisition Be Required, If so, how much?
Yes, unknown at this time. Fire has identified possible sites for the new fire facility.
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the planning and
construction of this facility.
Economic Development Impact: Indirectly
Tourism Impact: Indirectly
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Yes, personnel for the maintenance and upkeep of facility. Amount unknown at this time.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Emergency Management Programs Assistance, FL DCA
Assistance to Firefighters Grant Program
Municipal Competitive Grant Program
Florida Emergency Medical Services Matching Grant
Flood Mitigation Assistance, FL DCA
Rapid Emergency Activation/Deployment
USFFA
Critical Infrastructure Protection Grants Program, US DoC
Pre -Disaster Mitigation Program, FEMA
First Responder Initiative Grant Program, FEMA
Targeted Capacity Expansion Grants to Address Mental Health Service Needs of Public Safety Workers Responding
to Terrorist Attacks, US DHHS SAMHSA
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
City of Miami Bond Program
Summary of Sub -Group Meeting
DraftlWorking Paper
Category:
Public Safety
Proposed Proiect:
Police Training Facility (Two Story Facility/80,00 sq.ft.)
Is this item expressly identified in the Proposed G O Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$10 Million
Projected Time Line:
Planning Phase
Design/Drawings/Engineering Phase
Bid Process
Construction Phase
Estimated Cost (Expenditure Required Per Year):
Year One:
$ 500,000
Year Two:
2,375,000
Year Three:
2,375,000
Year Four:
2,375,000
Project Total:
$10,000,000
PROJECT CRITIERA
4 Months
8 Months
60 — 90 Days
18 — 36 Months
Planning/Design/Drawings/Engineering
Initial Construction of Facility
Construction of Facility
Completion of Construction
Will Land Acquisition Be Required, If so, how much? No, if current "Dustbowl" Site is utilized. Yes, if alternative sites considered.
Amount of land acquisition unknown at this time.
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority owned businesses
and the City's First Source Hiring Agreement when selecting vendors to provide for the planning and construction of this facility.
Economic Development Impact: Indirectly
Tourism Impact: Indirectly
Operational Impact (Once completed, will this project require additional funding from the City of Miami to Operate?): Yes, as it
relates to personnel to provide maintenance and upkeep of facility as well security personnel. Amount unknown at this time.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Critical Infrastructure Protection Grants Program, US DoC
First Responder Initiative Grant Program, FEMA
Targeted Capacity Expansion Grants to Address Mental Health Service Needs of Public Safety Workers Responding to Terrorist
Attacks, US DHHS SAMHSA
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
NOTE: This project scope could expand, if the City of Miami Police Department pursues a comprehensive training facility that will be
utilized to provide Homeland Domestic Security Training to other Local, State and Federal Law Enforcement Agencies. Consideration is
also being given to provide training to Caribbean and Latin American Law Enforcement Agencies, possibly through a U.S. State
Department program. This concept would require additional building structure, parking, field training areas and possibly a driving range.
Additional personnel would also be required. It is possible that Federal agency funding commitments, grants or legislatively earmarked
funding could be committed toward this concept. Many agencies would pay for attendance at these courses.
This concept would take a much longer time to pursue. Getting Federal funding, firm agency commitments, then developing a
comprehensive plan would require considerable time. Land acquisition would also add time to the project. This additional time may
prevent the Police Department use of these much needed training facilities for development of our MPD personnel.
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Project:
Little Haiti Park
Is this item expressly identified in the Proposed G.O. Bond Issue List of Protects?
Yes
Total Amounted Allocated:
$25 Million
PROJECT CRITIERA
Projected Time Line: The actual time line for this project is contingent upon the future development and eventual site of
the Little Haiti Park. However, the administration is committed to dedicating the necessary resources to move this project
forward in a timely fashion.
Estimated Cost (Expenditure Required Per Year):
Year One: $12,000,000 Land Acquisition
100,000 YMCA (Project Manager)
Year One: 500,000 Planning/Design/Engineering
Remaining Balance: $12,400,000
Will Land Acquisition Be Required, If so, how much? Yes — 25 acres at a minimum and 50 acres maximum. The
program components will drive the actual size of the Park. The conceptual boundaries of the first-class park in Little Haiti
are from NE 59th to NE 67th Streets, between NE 2nd Avenue and the railroad tracks. (See Attached Resolution # 01-1029)
Job Creation Potential (First Source Hiring Agreement): The administration should seriously consider, whenever
possible, utilizing the services of locally owned firms, minority owned businesses and the City's First Source Hiring
Agreement when selecting vendors to provide for the planning and construction of this facility.
Economic Development Impact: Yes
Tourism Impact: Yes. It is projected that the "Little Haiti Park" will be a major international tourist destination.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Additional park staff will be required to properly service the park, to date exact amount is unknown.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Tax Credits for Historic Buildings, FL DOS BHP
Brownfield Revolving Loan Program, SFLRPC
Brownfield Economic Development Initiative, HUD
Brownfield Property Ownership Clearance Assistance
Revolving Loan Program, FL GOV
UST Fields Pilot Program, EPA
Unique & Innovative Program, FL DEP
Petroleum Contamination Site Cleanup, FL DEP
Historic Preservation Small Matching Grant, FL DOS
BHP
Historic Preservation Special Category Grant, FL DOS
BHP
TEA -21 (Transportation Enhancement Program)
FDOT/MPO
Safe Neighborhood Bond Program
The Conservation Fund: American Greenways Program
National Tree Trust
Bricks and Mortar Challenge, Kresge Foundation
Predevelopment Loan Program, FL Housing Finance
Corporation
Dislocated Worker Employment & Training Program
Martin Luther King Day Initiative Grant, Corp. for
National and Community Service
Urban & Community Forestry Grants, FL DAG&CS
FL Recreation Development Assistance Program, FL
DEP
Florida Forever Grant Program, FL DEP
Land & Water Conservation Fund, FL DEP
FL Greenways & Trails, FL DEP
Renewable Communities Grant, HUD
2002 Challenge Cost -Share Program, US DAG
HBCU Assisting Communities Program, HUD
Aspire Higher Grant, Women's Sports Foundation
Physical Education for Progress Gra,. rogram, US
DofED
Recreational Programs for Individuals with Disabilities,
US DofED
Arts in Education Model Development and
Dissemination Grant, US DofED
Community Technology Centers Program, US DofED
Cultural Partnerships for At -Risk Children and Youth, US
DofED
Public Safety Impact: Yes
Community Planr_ig and Assistance Grant, FL DCA
Power -Up Grant Program, AOL/Time Warner
Foundation
Family Literacy Grants, Barbara Bush Foundation
National Youth Sports Program, US DHHS
The Charles A. and Anne Morrow Lindbergh Foundation
Grants
Carol M. White Physical Education Program, US DoED
Synergistic Relationship Between Bond vs. Non Bond Projects: Yes
2
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Project:
Historic Virginia Key Beach Park
Renovation of All Existing Buildings in the Park (including water/sewer improvements)
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$5 Million
PROJECT CRITIERA
It'iDt
Projected Time Line: Comp
--Phase I and II: Schematic Design and development
08/02
--Phase III: Construction documents (50%)
10/02
--Phase II: Construction documents (100°/x)
11/02
--City Review and approval
12/02
--Permit Filing (dry run)
01/03
--City of Miami and WASA agreement for sewer connection; preliminary layout of routing;
review and approval; sewer pump station, force main, and roadway construction
documents; ;plan processing through WASA, DERM, SFWMD
05/03
--Phase IV: Bidding and Negotiation
06/03
--Phase V: Construction Administration
12/03
Estimated Cost (Expenditure Required Per Year):
Year One: $ 500,000 Planning/Designing/Engineering
Year Two: 2,250,000 Renovation and Construction
Year Three: 2,250,000 Renovation and Construction
Note: Estimated cost of project is $1 million for renovation of existing buildings. Remaining funds requested
to be applied toward park furnishings such as picnic tables and benches, playground equipment, new
buildings (bathrooms, concession stands, stage, civil rights museum) lighting, resurfacing of parking area,
etc.
Will Land Acquisition Be Required, If so, how much? No
Job Creation Potential (First Source Hiring Agreement): The administration (Trust) should seriously
consider, whenever possible, utilizing the services of locally owned firms, minority owned businesses and
the City's First Source Hiring Agreement when selecting vendors to provide for the planning and
construction of this facility.
Economic Development Impact: Yes
Tourism Impact: Yes
Operational Impact (Once completed, will this project require additional funding from the City of
Miami to Operate?): Additional Park staff will be required to date amount unknown. Please note that the
Trust is expected to assume management and operation responsibilities upon completion of the renovation
and re -opening of the Park.
List Potential Grants that May Be Utilized to Off -Set Cost of this Project:
See Attachment (Potential Grants and Timetable Chart)
Note: The Trust is extremely aggressive as it relates to the pursuit and ultimate reward of grant dollars. To
date, two grants, totaling $800,000 have been submitted to federal agencies to assist with the cost of
renovating existing structures at the Park. (Details are included in the above referenced Chart). Also, listed
below is a list other possible grants:
Land and Water Conservation Fund, FL DEP
DRP
Urban Park & Recreation Recovery, NPS
Save America's Treasures, NEA/NPS
Historic Preservation Special Category Grant,
FL DOS BHP
Historic Preservation Small Matching Grant, FL
DOS BHP
Martin Luther King Day Initiative Grant, Corp. for
National and Community Service
Urban & Community Forestry Grants, FL
DAG&CS
FL Recreation Development Assistance
Program, FL DEP
FL Coastal Management Grants, FL DCA
FL Inland Navigation District Waterways
Program
FL Challenge Grant Program, FL DOS DCultA
Historical Resources Grant -in -Aid Museum
Grants, FL DOS
TEA -21 (Transportation Enhancement Program)
FDOT/MPO
Safe Neighborhood Bond Program
Public Safety Impact:
Yes
The Conservation Fund: American Greenways
Program
National Tree Trust
Kresge Foundation
Pew Charitable Trust
Ford Motor Company, Arts & Humanities
Program
Marine Turtle Grants Program
Urban Tree Planting Grants
Coastal Partnerships Initiative
Nature/Heritage Tourism Grant Program, FL
Comm on Tourism
The Charles A. and Anne Morrow Lindbergh
Foundation Grants
HBCU Assisting Communities Program, HUD
Beach Access Signs, FL DCommA
Endangered and Threatened Native Flora
Grants, FL DAG&CS
National Endowment for the Arts, (Part D)
Heritage and Preservation
National Endowment for the Arts, (Part C)
Access
Synergistic Relationship Between Bond vs. Non Bond Projects:
Army Corps of Engineers $5 Million Shoreline and Environmental Restoration — to begin
08/02
Miami -Dade County $5 Million To assist with the cost of the Civil Rights Museum
State of Florida $7,500 Development of a comprehensive historic
Preservation plan for the Park (July 02 — June 03)
2
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Categorv:
Parks and Recreation
Proposed Proiect:
Bicentennial Park Improvements
Is this item expressly identified in the Proposed G.O. Bond Issue List of Protects?
Yes
Total Amounted Allocated:
$10 Million
PROJECT CRITIERA
Projected Time Line: The actual time line for this project is contingent upon the future development decisions concerning
Bicentennial Park (see Miami Herald article of 4/8/02). However, there are some environmental concerns and significant
infrastructure improvements that must be completed prior to any development at Bicentennial Park and the administration is
willing to commit the necessary resources to move this project forward.
Estimated Cost (Expenditure Required Per Year):
Year One: $150,000 Phase II Environmental Testing Including Remediation Plan
Time Line: 3 Months Maximum
Year Two: $300,000 Environmental Clean Up and Removal/Encapsulation
Year Two: $500,000 Removal of Berms and Leveling of Land to Allow for Sightlines to the Bay
Will Land Acquisition Be Required, If so, how much? None -- But extensive infrastructure improvements are needed,
i.e., installation of water/sewer, electrical lines.
Job Creation Potential (First Source Hiring Agreement): The administration should seriously consider locally owned
firms, minority owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide the
infrastructure improvements necessary. Once development is completed, consultants have projected the creation of 1700
jobs (see Miami Herald article 4/8/02).
Economic Development Impact: Yes. The approved project has the potential to provide a synergy between the Park and
the Performing Arts Center, even extending across to Watson Island as destination points.
Tourism Impact: It is projected that the "new Bicentennial Park would be a major international tourism destination.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Additional staff will be required, to date number is unknown.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Land & Water Conservation Fund — Development, FL Nature/Heritage Tourism Grant Program, FL Comm on
DEP Tourism
Technology Opportunities Grants, US DofCOMM Knight Foundation: Community Partners Program
FL Inland Navigation District The Charles A. and Anne Morrow Lindbergh Foundation
Waterfronts Florida Partnership Grants Grants
Florida Cultural Endowment, FLHC Hispanic Serving Institutions Assisting Communities
Cultural Facilities Grants, FL DoS Program (HSIAC), HUD
Coastal Partnerships Initiative HBCU Assisting Communities Program, HUD
Safe Neighborhoods National Endowment for the Arts, (Part D) Heritage and
Preservation
Note: Bayfront Trust has committed $85,000 for the removal of the berms at BCP.
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: Yes
City of Miami Bond Program
Summary of Sub -Group Meeting
DraftlWorking Paper
Categorv:
Parks and Recreation
Proposed Project:
Jose Marti/East Little Havana Park Expansion
Is this item expressly identified in the Proposed G.O. Bond Issue List of Protects?
Yes
Total Amounted Allocated:
$5 Million
PROJECT CRITIERA
Projected Time Line:
Unknown at this time. The administration is of the opinion that the Parks Master Plan should drive the development,
expansion, and/or improvements to this vital green space. The Parks Master Plan would also take into consideration the
possible relocation of the East Little Havana NET office to Jose Marti Park making it accessible to the neighborhood.
Estimated Cost (Expenditure Required Per Year):
Unknown
Will Land Acquisition Be Required, If so, how much?
Unknown
Job Creation Potential (First Source Hiring Agreement):
Unknown
Economic Development Impact:
Unknown
Tourism Impact:
Unknown
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Unknown
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Land & Water Conservation Fund — Development, FL
Nature/Heritage Tourism Grant Program, FL Comm on
DEP
Tourism
Technology Opportunities Grants, US DofCOMM
Knight Foundation: Community Partners Program
FL Inland Navigation District
The Charles A. and Anne Morrow Lindbergh Foundation
Waterfronts Florida Partnership Grants
Grants
Florida Cultural Endowment, FLHC
Hispanic -Serving Institutions Assisting Communities
Cultural Facilities Grants, FL DoS
Program (HSIAC), HUD
Coastal Partnerships Initiative
HBCU Assisting Communities Program, HUD
Safe Neighborhoods
National Endowment for the Arts, (Part D) Heritage and
Preservation
Public Safety Impact: Unknown
Synergistic Relationship Between Bond vs. Non Bond Projects: Unknown
City of Miami Bond Program
Summary of Sub -Group Meeting
DraftlWorking Paper
Category:
Parks and Recreation
Proposed Project:
Margaret Pace Park
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$4 Million
PROJECT CRITIERA
Projected Time Line:
Phase I Planning/Design/Engineering Complete
Initial Construction Ongoing
Partial Park Opening July 4, 2002
Phase II Construction of Bathrooms/Pavilions 12 Months
Park Furnishings/Recreational Amenities
Estimated Cost (Expenditure Required Per Year):
Year One: $1.8 Million Reimbursement of Funds Already Expended
Year Two: $2.1 Million Construction of Bathrooms/Pavilions/Park Furnishings/Recreational Amenities
Will Land Acquisition Be Required, If so, how much?
No
Job Creation Potential (First Source Hiring Agreement):
N/A
Economic Development Impact:
Yes
Tourism Impact:
Yes
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Additional Park staff will be required to provide support for the services being offered at the Park, i.e.,
basketball and tennis courts. Amount unknown at this time.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Land & Water Conservation Fund — Development, FL
DEP
Technology Opportunities Grants, US DofCOMM
FL Inland Navigation District
Waterfronts Florida Partnership Grants
Florida Cultural Endowment, FLHC
Cultural Facilities Grants, FL DoS
Coastal Partnerships Initiative
Safe Neighborhoods
Nature/Heritage Tourism Grant Program, FL Comm on
Tourism
Public Safety Impact: Yes
Knight Foundation: Community Partners Program
The Charles A. and Anne Morrow Lindbergh Foundation
Grants
Hispanic -Serving Institutions Assisting Communities
Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
National Endowment for the Arts, (Part D) Heritage and
Preservation
Synergistic Relationship Between Bond vs. Non Bond Projects: Yes
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Project:
Soccer Complex
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$10 Million
PROJECT CRITIERA
Projected Time Line:
Depends on proposed development. General consensus seems to be to have the Mayor and Commission create an
advisory board (working group) comprised of experts in the field and appropriate city staff to look at this issue in greater
detail. Other options included using a portion of the proceeds to develop a soccer field(s) or a mini complex in the Little
Haiti Park.
Estimated Cost (Expenditure Required Per Year):
Year One: TBD
Year Two: TBD
Year Three: TBD
Will Land Acquisition Be Required, If so, how much?
Possibly
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the planning and
construction of this facility.
Economic Development Impact:
Yes
Tourism Impact:
Yes
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Possibly — maintenance and upkeep of facility.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
• The best way to leverage the bond money in this case is to seek a "naming rights" opportunity with a sports
equipment, sports drink, or soft drink company. Possibilities include Adidas, NIKE, Puma, Sondico, Coca Cola,
Pepsi, Gatorade, Tropicana, and Postobon. Other possibilities include AT & T Cable Services, airlines (Iberia,
VARIG, VASP, Aeromexico, TACA), and Western Union.
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: N/A
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Prosect:
Citywide Waterfront Improvements
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$10 Million
PROJECT CRITIERA
Projected Time Line:
See Below
Estimated Cost (Expenditure Required Per Year):
Year One: $250,000 Assessment of seawalls, boat ramps, boardwalks, streets that abut
water and waterfront parks to determine repair/replacement needs.
15,000 Hire consultant to inspect all 3000 pilings and finger pilings and develop
replacement plan.
100,000 Immediately replace 100 pilings that are severely deteriorated that present an
existing hazard.
Year Two: TBD Expenditures based upon the results of the assessment.
Possible Projects Mentioned: Anchorage (Install Moorings $500,000)
Dock Master Office ($250,000)
Dingy Dock ($100,0000)
Seawall Restoration/Replacement: Watson Island, Marine Stadium Marina, and
Bicentennial Park
Will Land Acquisition Be Required, If so, how much? No
Job Creation Potential (First Source Hiring Agreement): The administration should seriously consider, whenever
possible, utilizing the services of locally owned firms, minority owned businesses and the City's First Source Hiring
Agreement when selecting vendors to provide the services required.
Economic Development Impact: Yes
Tourism Impact: Yes
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Possibly — maintenance.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Land & Water Conservation Fund — Development, FL Florida Hurricane Loss Mitigation Program, FL Bur of
DEP Recovery & Mitigation
FL Inland Navigation District Small Navigation Projects, US Army Corps of Engineers
Waterfronts Florida Partnership Grants Economic Development Assistance Grants (Various
FL Coastal Management Grants, FL DCA Categories), US DoCOMM EDA
Coastal Partnerships Initiative, FLDCA Beach Access Signs, FL DCommA
The Clean Vessel Act, FL DEP
Public Safety Impact: Yes, the anchorage presents a navigational hazard to the boating community.
Synergistic Relationship Between Bond vs. Non Bond Projects: Yes
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Project:
Marine Stadium
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$2 Million
PROJECT CRITIERA
Projected Time Line:
Depends on proposed development. The administration is of the opinion that the $2 million dollars should be invested into
addressing the infrastructure needs at Marine Stadium; thereby, allowing the property to increase in value and viability for
development.
Estimated Cost (Expenditure Required Per Year):
Year One: TBD
Year Two: TBD
Year Three: TBD
Will Land Acquisition Be Required, If so, how much?
No
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the planning and
improvements to this facility.
Economic Development Impact:
Yes
Tourism Impact:
Yes
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Unknown
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
FL Inland Navigation District
Waterfronts Florida Partnership Grants
Florida Cultural Endowment, FLHC
Cultural Facilities Grants, FL DoS
Coastal Partnerships Initiative
FL Recreation Development Assistance Program, FL DEP
FL Coastal Management Grants, FL DCA
Economic Development Assistance Grants (Various Categories), US DoCOMM EDA
The Clean Vessel Act, FL DEP
Public Safety Impact: Unknown
Synergistic Relationship Between Bond vs. Non Bond Projects: Unknown
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Project:
Neighborhood Park Improvements and Acquisition
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$31 Million
PROJECT CRITIERA
Projected Time Line: Initially, P/R submitted a proposed list of projects totaling more than $21 million. After a great deal
of discussion and constructive debate it was decided that the Parks Master Plan should drive the expenditure of the
majority of the $31 Million. However, there are some park related projects that need to be addressed within the next 6 — 18
months (See attached list).
Estimated Cost (Expenditure Required Per Year): See Attached List.
Will Land Acquisition Be Required, If so, how much? See Attached List
Job Creation Potential (First Source Hiring Agreement): The administration should seriously consider, whenever
possible, utilizing the services of locally owned firms, minority owned businesses and the City's First Source Hiring
Agreement when selecting vendors to provide for the planning/improvements/ and/or construction of these park related
facilities.
Economic Development Impact: Yes
Tourism Impact: Yes
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Additional staff or funding may be required to maintain these facilities.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Pathways to Nature Conservation Fund Program, US Dol
Historic Preservation Special Category Grant, FL DOS
FMC Corporation Bird and Habitat Conservation Fund, US
BHP
Historic Preservation Small Matching Grant, FL DOS BHP
Dol
Recreational Trails Grants, FL DEP
Martin Luther King Day Initiative Grant, Corp. for National
Recreational Trails Program, US DoT
Land & Water Conservation Fund — Acquisitions, FL DEP
and Community Service
Urban & Community Forestry Grants, FL DAG&CS
Land & Water Conservation Fund — Development, FL DEP
FL Recreation Development Assistance Program, FL DEP
Technology Opportunities Grants, US DofCOMM
FL Coastal Management Grants, FL DCA
FL Inland Navigation District
TEA -21 (Transportation Enhancement Program)
National Youth Sports Program, US DHHS
FDOT/MPO
Florida Boating Improvement Program Grants, FL FWCC
Safe Neighborhood Bond Program
NEA Access Grants, US NEA
The Conservation Fund: American Greenways Program
National Endowment for the Arts, (Part D) Heritage and
National Tree Trust
Preservation
Hasbro Children's Foundation
Manatee Planning Grants, FL FWCC
Nature/Heritage Tourism Grant Program, FL Comm on
NIKE
Adidas
Tourism
Adult Education and Family Literacy, FL DoE
Puma
Small Navigation Projects, US Army Corps of Engineers
Coca Cola
Waterfronts Florida Partnership Grants, FL DCA
Pepsi
The Charles A. and Anne Morrow Lindbergh Foundation
Knight Foundation: Community Partners Program
Grants
Dade Community Foundation
Hispanic -Serving Institutions Assisting Communities
Florida Forever
Program (HSIAC), HUD
Community Technology Grants, FL DoED
HBCU Assisting Communities Program, HUD
Law Enforcement Trust Fund
The Clean Vessel Act, FLDEP
Urban Park & Recreation Recovery, NPS
Carol M. White Physical Education Program, US DoED
Save America's Treasures, NEA/NPS
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: Yes
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Prosect:
Fern Isle Cleanup and Renovation
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$9 Million
PROJECT CRITIERA
Projected Time Line:
The projected time line for the renovation and/or expansion of Fern Isle is directly linked to the timetable involved for the
testing, removal and cleanup of this facility. Listed below is a yearly breakdown of dollar allocation and service to be
provided.
Estimated Cost (Expenditure Required Per Year):
Year One: $300,000 Assessment/Testing and Remediation Plan 4-6 Months
Year Two: $3 Million Cleanup and Removal
Year Three: $1 Million Mitigation/Initial Construction (If So Desired)
Will Land Acquisition Be Required, If so, how much?
No
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the assessment and
remediation of this facility.
Economic Development Impact:
Yes
Tourism Impact:
Yes
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Additional staff or funding may be required to maintain this facility.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Brownfield Revolving Loan Program, SFLRPC
Brownfield Economic Development Initiative, HUD
Urban Park & Recreation Recovery, NPS
Small Quantity Hazardous Waste Generator Grant, FL DEP
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects:
N/A
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Parks and Recreation
Proposed Proiect:
Orange Bowl Improvements
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
Yes
Total Amounted Allocated:
$16 Million
PROJECT CRITIERA
Projected Time Line:
This historic facility is in dire need of structural improvements, some of which have already begun. However, the final
improvements/expansion/development will be determined in greater detail by a consultant's report, which will identify the
best possible maximization of Orange Bowl resources.
Estimated Cost (Expenditure Required Per Year):
Year One: $150,000 — 300,000 Develop Business and Market Analysis Plan 9-12 Months
Year One: $1,600,000 Structural Repairs
Assumption: The Business Plan will determine the marketing opportunities, necessary renovations, estimated renovation
costs, and funding opportunities. Once the business plan is complete, the funding plan and the timeline for renovations will
be prepared and submitted for consideration.
Will Land Acquisition Be Required, If so, how much? No
Job Creation Potential (First Source Hiring Agreement):
The administration should seriously consider, whenever possible, utilizing the services of locally owned firms, minority
owned businesses and the City's First Source Hiring Agreement when selecting vendors to provide for the planning
design/and renovation of this facility.
Economic Development Impact: Yes
Tourism Impact: Yes
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
Operate?): Additional staff or funding may be required to maintain this facility.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Possible Partnerships being considered with MSEA, University of Miami, and/or Miami -Dade County.
CDT as a possible funding source was also discussed.
State Funding
Public Safety Impact: Yes
Synergistic Relationship Between Bond vs. Non Bond Projects: Yes
Honorable Mayor
Members of the Commission
r
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
-ATE
May 6, 2002
SLa,:ECT Bond Issue — Streets and
Drainage
REFERENCES
ENCLOSURES.
FILE
As part and parcel of the Homeland Defense/Neighborhood Improvement Bond Program, the
category dealing with Streets and Drainage was sub -divided into eight areas of interest:
✓ Flagami Storm Water Mitigation
$10 Million
✓ Grand Avenue Improvements
3 Million
✓ Coral Way Improvements
3 Million
✓ Calle Ocho Improvements
6 Million
✓ NE 2nd Avenue Improvements (36th St. to 78th St.)
6 Million
✓ Model City Infrastructure Improvements
6 Million
✓ Design District/FEC Corridor Improvements
10 Million
✓ Downtown Infrastructure Improvements
10 Million
Since the approval of the Bond Program, the administration has had the opportunity to thoroughly
review each of these areas of interest and concluded that additional guidance and policy direction
is needed from the elected leadership of the City Miami (City) prior to moving forward with
possible recommendations.
Each category listed above, except for the Flagami Strom Water Mitigation Project, is either in the
planning, design, or conceptual stage of development. It is imperative that we ascertain vital
information from each of the involved parties; thereby, allowing us to move forward on these
projects in a timely and efficient manner. The administration is of the opinion that by taking a
project -by -project review, it will provide for the maximization of municipal resources and enhance
the nature of each of these projects.
Therefore, it is the recommendation of the Administration that we, the Administration and the
elected leadership of the City of Miami, workshop this particular issue in greater detail.
Cc: Frank Rollason, Assistant City Manager
Dena Bianchino, Assistant City Manager
Bob Nachlinger, Assistant City Manager
Genaro "Chip" Iglesias, Chief of Staff
Ronda A. Vangates, Special Assistant
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
Honorable Mayor -,7--
Members of the Commission May 6, 2002
"Sjt'�T Bond Issue -- Quality of Life
r os z �EFEFEr,cEs
City Manage
`aCLCSURE
FILE
As part and parcel of the Homeland Defense/Neighborhood Improvement Bond Program, the
category dealing with Quality of Life Issues was sub -divided into five areas:
✓ Neighborhood Quality of Life Improvements $25 Million
✓ Greenways 2 Million
✓ Museum of Science 3.5 Million
✓ Museum of Art 3.5 Million
✓ Neighborhood Gateways 4 Million
Since the approval of the Bond Program, the administration has had the opportunity to thoroughly
review each of these sub -categories and concluded that additional guidance and policy direction
is needed from the elected leadership of the City Miami (City) prior to moving forward with
possible recommendations.
Each category however, does present a unique and rare opportunity for the City to maximize its
resources and to wisely invest in improving the aesthetics of the City, providing unique gateways
into historic neighborhoods and frequently traveled entrances into the City, as well as providing
scenic greenways and developing a world class Museum of Art and Science.
Therefore, it is the recommendation of the Administration that we, the administration and the
elected leadership of the City of Miami, workshop this particular issue in greater detail.
Cc: Frank Rollason, Assistant City Manager
Dena Bianchino, Assistant City Manager
Bob Nachlinger, Assistant City Manager
Genaro "Chip" Iglesias, Chief of Staff
Ronda A. Vangates, Special Assistant
City of Miami Bond Program
Summary of Sub -Group Meeting
DraftlWorking Paper
Category:
Historic Preservation $5 Million Total Allocation
Proposed Project:
Historic Resources Survey and Designation Reports
This project includes a comprehensive citywide historic resources survey and the preparation of designation reports for
historic sites and districts. Historic resources surveys form the cornerstone of all historic preservation efforts. Most
historic and archaeological resources are initially identified through a survey. In the City of Miami, there are approximately
55,000 parcels that were built prior to 1960. In order to have a truly successful preservation program, a community must
initially establish the value and significance of its historic resources through a field survey. A survey results in an
inventory of information on specific properties evaluated as significant. Inventories contain information on historic and
archeological resources identified during the survey, as well as areas surveyed that do not contain historic properties.
Properties identified during the survey process provide the information base from which preservation professionals
evaluate properties for historic designation. The results of a survey are also integrated into the comprehensive planning
process so that planning and land -use decisions are based on all available information.
A comprehensive historic resources survey expedites the permitting of new development, as well as the rehabilitation of
historic properties. It facilitates the designation process and assists homeowners and neighborhood associations that
request historic designation.
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
No
PROJECT CRITERIA
Projected Time Line:
5 years
Estimated Cost (Expenditure Required Per Year):
Year One: $200,000
Year Two: 200,000
Year Three: 200,000
Year Four: 200,000
Year Five: 200,000
Project Total: $1,000,000
Will Land Acquisition Be Required? If so, how much? No
Job Creation Potential (First Source Hiring Agreement): Minimal
Economic Development Impact:
Historic designation enhances property values and stimulates private investment in an area.
Tourism Impact:
Heritage and cultural tourism is the fastest-growing segment of the tourism industry. Forty-six percent of all U.S. adult
travelers included a cultural, arts, heritage or historic activity while on a trip during the previous year. Of these travelers,
visiting a historic site was the most popular cultural activity. Visitors to historic sites stay longer and spend more money
than other kinds of tourists. For example, while the average U.S. traveler spends $425 and 3.3 nights away from home
per trip, visitors to historic and cultural attractions sites spend $615 and 4.7 nights. Their spending can help diversify a
local economy and preserve the community's character.
Operational Impact (Once completed will this project require additional funding from the City of Miami to
operate?):
One additional staff member in the Planning and Zoning Department may be required to process applications for
Certificates of Appropriateness for properties in new historic districts that may be designated.
List Potential Grants that Maybe Utilized to Offset Cost of this Proiect:
Funding Source Grant Title Application Solicitation Period
FL Division of Historical Resources Historic Preservation Small Matching October 1 — December 15
Grants
Additional Grant Opportunities:
Florida Local History Records Grant Program, FL DoS
Save America's Treasures
Bricks & Mortar Challenge, Kresge Foundation
Historical Resources Grant Programs: Special Category Grants, FL DoS
Knight Foundation: Community Partners Program
Hispanic -Serving Institutions Assisting Communities Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
Cultural Facilities Grants, FL DoS
Graham Foundation Grant Programs
National Endowment for the Arts, (Part D) Heritage and Preservation
Public Works & Economic Development, US DoCOMM, EDA
Public Safety Impact:
When neighborhoods are designated as historic districts, they generally become more desirable places to live, and public
safety is enhanced.
Synergistic Relationship Between Bond vs. Non Bond Projects:
This will continue the current survey and designation activity that is underway using Community Development funds. It
will further complement the renewed effort by the Miami -Dade County Historic Preservation Office to update the Dade
County Historic Survey, which was completed in 1978. The City has relied on this survey, which has not been updated in
25 years.
2
City of Miami Bond Program
Summary of Sub -Group Meeting
DraftlWorking Paper
Category:
Historic Preservation
Proposed Project:
Former Black Police Precinct - Rehabilitation
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
No
Total Amount Allocated:
$500,000 out of a total estimated cost of $1.1 million
PROJECT CRITERIA
Projected Time Line:
This project includes a contribution to the rehabilitation of the former Black Police Precinct for use as a museum and
center for youth activities in Overtown. Completion Time: 2 years
Estimated Cost (Expenditure Required Per Year):
Year One: $250,000
Year Two: 250,000
Project Total: $500,000
Will Land Acquisition Be Required? If so, how much?
No. The building is owned by the City.
Job Creation Potential (First Source Hiring Agreement):
The rehabilitation project may create construction jobs. Once completed, local users of the center could generate
incidental employment, such as docents and others who would conduct programs in the building.
Economic Development Impact:
The rehabilitation of the building could serve as a catalyst in the revitalization of Overtown. Studies show that $1 million
spend on non-residential historic rehabilitation generates $79,000 more in income and $110,000 more in wealth than the
same amount of money spent on new construction.
Tourism Impact:
Heritage and cultural tourism is the fastest-growing segment of the tourism industry. Forty-six percent of all U.S. adult
travelers included a cultural, arts, heritage or historic activity while on a trip during the previous year. Of these travelers,
visiting a historic site was the most popular cultural activity. Visitors to historic sites stay longer and spend more money
than other kinds of tourists. For example, while the average U.S. traveler spends $425 and 3.3 nights away from home
per trip, visitors to historic and cultural attractions sites spend $615 and 4.7 nights. Their spending can help diversify a
local economy and preserve the community's character.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
operate?):
The City will likely continue to be responsible for maintaining the building, although the operation of the building would be
the responsibility of the lessee.
List Potential Grants that Maybe Utilized to Offset Cost of this Project:
Funding Source
Grant Title
Application Solicitation Period
FL Division of Historical Resources
Historic Preservation Small Matching
Grants
October 1 — December 15
FL Division of Historical Resources
Historic Preservation and Historical
Museums Special Category Grants
April 1 — May 31
FL Division of Historical Resources
Historical Museums Small Matching
Grants
October 1 —December 15
Additional Grant Opportunities:
Florida Local History Records Grant Program, FL DOS
Save America's Treasures
Bricks & Mortar Challenge, Kresge Foundation
Historical Resources Grant Programs: Special Category Grants, FL DOS
Knight Foundation: Community Partners Program
Hispanic -Serving Institutions Assisting Communities Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
Cultural Facilities Grants, FL DOS
Graham Foundation Grant Programs
National Endowment for the Arts, (Part D) Heritage and Preservation
Public Works & Economic Development, US DoCOMM, EDA
Public Safety Impact:
The establishment of a museum and center for youth activities in Overtown will generate activity, thereby increasing
safety in the immediate neighborhood.
Synergistic Relationship Between Bond vs. Non Bond Projects:
This project will continue the revitalization efforts currently underway in Overtown by such agencies as the CRA and the
Black Archives History and Research Foundation.
2
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Historic Preservation $5 Million Total Allocation
Proposed Prosect:
City Hall — Rehabilitation of City Commission Chambers
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
No
PROJECT CRITERIA
Projected Time Line:
The project involves the restoration of the ceiling, murals and beams in the City Commission chambers, as part of an
overall upgrade of the chambers, including a new sound and lighting system. The project could lead to a more
comprehensive rehabilitation of the building. Completion Time: 2 years
Estimated Cost (Expenditure Required Per Year):
Year One: $ 50,000 (analysis of existing conditions and development of drawings)
Year Two: $200,000 (completion of work)
Project Total: $250,000
Will Land Acquisition Be Required? If so, how much?
No. The building is owned by the City.
Job Creation Potential (First Source Hiring Agreement):
The rehabilitation project may create specialized construction jobs.
Economic Development Impact:
Studies show that $1 million spend on non-residential historic rehabilitation generates $79,000 more in income, and
$110,000 more in wealth than the same amount of money spent on new construction.
Tourism Impact:
As the former Pan American Terminal Building, City Hall is a tourist destination in Coconut Grove. Heritage and cultural
tourism is the fastest-growing segment of the tourism industry. Forty-six percent of all U.S. adult travelers included a
cultural, arts, heritage or historic activity while on a trip during the previous year. Of these travelers, visiting a historic site
was the most popular cultural activity. Visitors to historic sites stay longer and spend more money than other kinds of
tourists. For example, while the average U.S. traveler spends $425 and 3.3 nights away from home per trip, visitors to
historic and cultural attractions sites spend $615 and 4.7 nights. Their spending can help diversify a local economy and
preserve the community's character.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
operate?):
None. The rehabilitation could eliminate some of the deferred maintenance that is ongoing.
List Potential Grants that Maybe Utilized to Offset Cost of this Project:
Funding Source
Grant Title
Application Solicitation Period
FL Division of Historical Resources
Historic Preservation Small Matching
Grants
October 1 — December 15
FL Division of Historical Resources
Historic Preservation and Historical
Museums Special Category Grants
April 1 — May 31
Additional Grant Opportunities:
Florida Local History Records Grant Program, FL DoS
Save America's Treasures
Bricks & Mortar Challenge, Kresge Foundation
Historical Resources Grant Programs: Special Category Grants, FL DoS
Knight Foundation: Community Pari . Program
Hispanic-Serving Institutions Assistir% Communities Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
Cultural Facilities Grants, FL DoS
Graham Foundation Grant Programs
National Endowment for the Arts, (Part D) Heritage and Preservation
Public Works & Economic Development, US DoCOMM, EDA
Public Safety Impact:
None
Synergistic Relationship Between Bond vs. Non Bond Projects:
This project will enhance the City's efforts to present itself in a favorable light, particularly on NET 9 during City
Commission and Board meetings. The restoration of the historic ceiling paintings in the Commission chambers will
present a dramatic backdrop on television.
2
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
Category:
Historic Preservation $5 Million Total Allocation
Proposed Project:
Gusman Theater - Completion of the Restoration of the Theater and Lobby
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
No
Total Amounted Allocated:
$500,000, out of a total estimated cost of $6 million
PROJECT CRITERIA
Projected Time Line:
This project will complete the restoration of the theater and lobby and will include those specialized restoration elements,
such as decorative painting, historic lighting and other similar elements for which the Department of Off -Street Parking
has been unable to obtain grant funding. Completion Time: 1 Year
Estimated Cost (Expenditure Required Per Year):
Year One: $500,000
Project Total: $500,000
Will Land Acquisition Be Required? If so, how much?
No. The building is owned by the City.
Job Creation Potential (First Source Hiring Agreement):
The restoration project may create specialized construction jobs.
Economic Development Impact:
Gusman Theater is the cornerstone in the revitalization of Downtown Miami. The completion of the restoration of the
theater will increase its marketability and provide a more inviting venue to attract residents and visitors to Downtown.
Gusman will continue to make the theater available to all groups within the community, as well as school children.
Tourism Impact:
Gusman Theater is a significant tourist destination in Downtown Miami, and could be a greater draw once the restoration
is completed. Heritage and cultural tourism is the fastest-growing segment of the tourism industry. Forty-six percent of all
U.S. adult travelers included a cultural, arts, heritage or historic activity while on a trip during the previous year. Of these
travelers, visiting a historic site was the most popular cultural activity. Visitors to historic sites stay longer and spend more
money than other kinds of tourists. For example, while the average U.S. traveler spends $425 and 3.3 nights away from
home per trip, visitors to historic and cultural attractions sites spend $615 and 4.7 nights. Their spending can help
diversify a local economy and preserve the community's character.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
operate?):
None. This project will simply complete the restoration of the theater that has been ongoing for many years.
List Potential Grants that Maybe Utilized to Offset Cost of this Project:
Fundinq Source
Grant Title
Application Solicitation Period
FL Division of Historical Resources
Historic Preservation Small Matching
Grants
October 1 — December 15
FL Division of Historical Resources
Historic Preservation and Historical
Museums Special Category Grants
April 1 — May 31
Additional Grant Opportunities:
Florida Local History Records Grant Program, FL DoS
Save America's Treasures
Bricks & Mortar Challenge, Kresge F dation
Historical Resources Grant Prograrrr�_- opecial Category Grants, FL DoS
Knight Foundation: Community Partners Program
Hispanic -Serving Institutions Assisting Communities Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
Cultural Facilities Grants, FL DoS
Graham Foundation Grant Programs
National Endowment for the Arts, (Part D) Heritage and Preservation
Public Works & Economic Development, US DoCOMM, EDA
Note:
The project has already received more than $2 million in grant funds from the Florida Department of State and $3.8 million
from Miami -Dade County. This project would include only those elements for which the Department of Off -Street Parking
has been unable to obtain additional grant funds.
Public Safety Impact:
The restoration of Gusman Theater and the increased usage that will result will increase activity in Downtown Miami,
thereby increasing safety.
Synergistic Relationship Between Bond vs. Non Bond Projects:
This project will complement the Flagler Marketplace project that has been underway for several years by the Downtown
Development Authority, as well as the Downtown revitalization projects that have been promoted by the City.
N
City of Miami Bond Program
Summary of Sub -Group Meeting
DraftlWorking Paper
Category:
Historic Preservation $5 Million Total Allocation
Proposed Project:
First Miami High School — Relocation/Rehabilitation
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
No
Total Amount Allocated:
$250,000, out of a total estimated cost of $1.1 million
PROJECT CRITERIA
Projected Time Line:
This project includes a contribution to the relocation and rehabilitation of Miami's first high school for use as a community
center in Southside Park. Completion Time: 1 Year/Relocation
Estimated Cost (Expenditure Required Per Year):
Year One: $250,000 out of a total estimated cost of $1.1 million
Project Total: $250,000
Will Land Acquisition Be Required? If so, how much?
No. The building will be donated to the City by the property owner and will be relocated to Southside Park, which is
owned by the City.
Job Creation Potential (First Source Hiring Agreement): The rehabilitation project may create construction jobs.
Once completed, local users of the community center could generate incidental employment, such as tutors, teacher
aides and others who would conduct programs.
Economic Development Impact: Studies show that $1 million spend on non-residential historic rehabilitation generates
$79,000 more in income and $110,000 more in wealth than the same amount of money spent on new construction.
Tourism Impact: Heritage and cultural tourism is the fastest-growing segment of the tourism industry. Forty-six percent
of all U.S. adult travelers included a cultural, arts, heritage or historic activity while on a trip during the previous year. Of
these travelers, visiting a historic site was the most popular cultural activity. Visitors to historic sites stay longer and
spend more money than other kinds of tourists. For example, while the average U.S. traveler spends $425 and 3.3 nights
away from home per trip, visitors to historic and cultural attractions sites spend $615 and 4.7 nights. Their spending can
help diversify a local economy and preserve the community's character.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
operate?): Although the Parks and Recreation Department will be responsible for staffing the building, the Parks
supervisor could relocate his/her office from Simpson Park to this building. The City will be responsible for maintaining
the building.
List Potential Grants that Maybe Utilized to Offset Cost of this Project:
Funding Source
Grant Title
Application Solicitation Period
FL Division of Historical Resources
Historic Preservation Small Matching
Grants
October 1 — December 15
FL Division of Historical Resources
Historic Preservation and Historical
Museums Special Category Grants
April 1 — May 31
Kresge Foundation
Bricks and Mortar Challenge Grant
Ongoing
Additional Grant Opportunities:
Florida Local History Records Grant Program, FL DoS
Save America's Treasures
Bricks & Mortar Challenge, Kresge Foundation
Historical Resources Grant Programs: Special Category Grants, FL DoS
Knight Foundation: Community Partners Program
Hispanic-Serving Institutions Assisting Communities Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
Cultural Facilities Grants, FL DoS
Graham Foundation Grant Programs
National Endowment for the Arts, (Part D) Heritage and Preservation
Public Works & Economic Development, US DoCOMM, EDA
Public Safety Impact:
The establishment of a community center in Southside Park will increase activity in the park, thereby increasing safety in
both the park and immediate neighborhood.
Synergistic Relationship Between Bond vs. Non Bond Projects:
The relocation of this building was first considered by the City Commission when the Major Use Special Permit for the
Brickell Station was approved. That project would require the demolition of the historic building. The City Commission
required that the developer prepare measured drawings of the building and assist in the relocation costs. This project will
ensure that Miami's first high school will not be demolished.
2
Category:
Historic Preservation
Proposed Project:
Historic Markers
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
$5 Million Total Allocation
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
No
Total Amount Allocated:
$50,000
PROJECT CRITERIA
Projected Time Line: This project will place markers on designated historic sites in the City of Miami. Although Miami
has begun a program to install markers at select historic sites, most of the properties that have been designated by the
City have no markers. The placement of markers on all locally designated historic properties will draw attention to these
buildings and increase public awareness of our history. Historic markers or plaques can also be placed in the City of
Miami Cemetery to identify those significant individuals buried there and the contribution they have made to the City.
Completion Time: 1 Year
Estimated Cost (Expenditure Required Per Year):
Year One: None
Year Two: $50,000
Project Total: $50,000
Will Land Acquisition Be Required? If so, how much? No
Job Creation Potential (First Source Hiring Agreement): Minimal
Economic Development Impact: Historic designation enhances property values and stimulates private investment in an
area.
Tourism Impact: A historic marker program can be a definite magnet for tourists. Heritage and cultural tourism is the
fastest-growing segment of the tourism industry. Forty-six percent of all U.S. adult travelers included a cultural, arts,
heritage or historic activity while on a trip during the previous year. Of these travelers, visiting a historic site was the most
popular cultural activity. Visitors to historic sites stay longer and spend more money than other kinds of tourists. For
example, while the average U.S. traveler spends $425 and 3.3 nights away from home per trip, visitors to historic and
cultural attractions sites spend $615 and 4.7 nights. Their spending can help diversify a local economy and preserve the
community's character.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
operate?): Minimal impact. The City will be required to maintain the markers.
List Potential Grants that Maybe Utilized to Offset Cost of this Project:
Funding Source
Grant Title
Application Solicitation Period
FL Division of Historical Resources
Historic Preservation Small Matching
Grants
October 1 — December 15
Additional Grant Opportunities:
Florida Local History Records Grant Program, FL DoS
Save America's Treasures
Bricks & Mortar Challenge, Kresge Foundation
Historical Resources Grant Programs: Special Category
Grants, FL DoS
Knight Foundation: Community Partners Program
Hispanic -Serving Institutions Assisting Communities
Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
Cultural Facilities Grants, FL DoS
Graham Foundation Grant Programs
National Endowment for the Arts, (Part D) Heritage and
Preservation
Public Works & Economic Development, US DoCOMM,
EDA
Public Safety Impact:
The new markers will identify historic properties, increasing identity and visibility.
Synergistic Relationship Between Bond vs. Non Bond Projects:
This will complement the historic marker program initiated by the Orange Blossom Initiative, approved by the City
Commission and partially funded by the City. This program will place markers on historic sites, most of which are no
longer standing. The project will further complement the markers that have been installed on Charles Avenue in Coconut
Grove and along the Miami River.
2
Category:
Historic Preservation
Proposed Prosect:
Historic District Street Signs
City of Miami Bond Program
Summary of Sub -Group Meeting
Draft/Working Paper
$5 Million Total Allocation
Is this item expressly identified in the Proposed G.O. Bond Issue List of Projects?
No
Total Amount Allocated:
$60,000
PROJECT CRITERIA
Projected Time Line: This project will replace existing street signs in the City's four historic districts with new, more
aesthetically pleasing signs that also contain the name of the historic district. Residents of the City's four historic districts
(Morningside, Buena Vista East, Bayside, Spring Garden) have repeatedly requested street signs that identify their
neighborhoods as historic and that also contain the original names of the streets. Completion Time: 1 Year
Estimated Cost (Expenditure Required Per Year):
Year One: $60,000
Project Total: $60,000
Will Land Acquisition Be Required? If so, how much? No
Job Creation Potential (First Source Hiring Agreement): Minimal
Economic Development Impact: In residential historic districts, property values appreciate significantly faster than the
market as a whole. Historic designation enhances property values and stimulates private investment in an area.
Tourism Impact: Heritage and cultural tourism is the fastest-growing segment of the tourism industry. Forty-six percent
of all U.S. adult travelers included a cultural, arts, heritage or historic activity while on a trip during the previous year. Of
these travelers, visiting a historic site was the most popular cultural activity. Visitors to historic sites stay longer and
spend more money than other kinds of tourists. For example, while the average U.S. traveler spends $425 and 3.3 nights
away from home per trip, visitors to historic and cultural attractions sites spend $615 and 4.7 nights. Their spending can
help diversify a local economy and preserve the community's character.
Operational Impact (Once completed, will this project require additional funding from the City of Miami to
operate?): Minimal impact. The City will be required to maintain the signs and pay for replacement signs as required.
List Potential Grants that Maybe Utilized to Off -Set Cost of this Project:
Funding Source
Grant Title
Application Solicitation Period
FL Division of Historical Resources
Historic Preservation Small Matching
Grants
October 1 — December 15
Additional Grant Opportunities:
Florida Local History Records Grant Program, FL DoS
Save America's Treasures
Bricks & Mortar Challenge, Kresge Foundation
Historical Resources Grant Programs: Special Category
Grants, FL DoS
Knight Foundation: Community Partners Program
Hispanic -Serving Institutions Assisting Communities
Program (HSIAC), HUD
HBCU Assisting Communities Program, HUD
Cultural Facilities Grants, FL DoS
Graham Foundation Grant Programs
National Endowment for the Arts, (Part D) Heritage and
Preservation
Public Works & Economic Development, US DoCOMM,
EDA
Public Safety Impact:
The new street signs will identify the neighborhoods as historic districts, increasing neighborhood identity and visibility.
Neighborhoods that are designated as historic districts generally are more desirable places to live, and public safety is
enhanced.
Synergistic Relationship Between Bond vs. Non Bond Projects:
This will complement the investment that is taking place in all four of the City's historic districts. Such street signs will
increase neighborhood identity and pride.
2
00
"
City of Miami
was
http.*//www_ci.rniarni.fl.us wagon
Manuel A. Diaz, Mayor
Com. Tomas Regalado, Chairman
Com. Johnny L. Winton, Vice -Chairman
Com. Angel Gonzalez
Com. Joe Sanchez
Com. Arthur E. Teele, Jr.
CAPITAL IMPROVEMENT PROGRAM
(CIP) WORKSHOP
Wednesday, May 08, 2002
Workshop Agenda
General Overview
Carlos Gimenez, City Manager
Financial Overview and update
Bob Nachlinger, Assistant City Manager
Discussion Regarding Proposed Projects
Adjournment
Notg: All Assistant City Managers, Department Directors as well as Attorney Albert
Gastil�glfd Counsel), are present to answer questions regarding proposed
I CIP Projects.
Scheider, Sylvia
From: Scheider, Sylvia
Sent: Tuesday, April 30, 2002 10:54 AM
To: Martinez, Alex; Stancato, Aldo
Cc: Ferguson, Paul; Pico, Hector; Block, Alison; Thompson, Priscilla A.; Rojas, Anna
Subject: FW: Workshop on Wednesday, May 8, 2002
Importance: High
Please make the necessary arrangements to cover the workshop mentioned below:
May 8, 2002
Hyatt Hotel, Jasmine Room, 400 S.E. 2nd Avenue
2:30 p.m.
GSA/Communications: We need to have communication technicians set up audio
equipment with microphones for Commissioners and the Administration. We will be
recording on tape recorder and laptop digital recorder.
IT: Please arrange to have either Hector or Alison present to assist in the installation
of the laptop digital recorder. It will be helpful if one of them could remain during the
meeting to assist if trouble should arise from the laptop recorder.
Thank you all very much!
-----Original Message -----
From: Lagace, Rita
Sent: Tuesday, April 30, 2002 10:48 AM
To: Davis, Yolanda
Cc: Thompson, Priscilla A.; Scheider, Sylvia; Rojas, Anna
Subject: FW: Workshop on Wednesday, May 8, 2002
Importance: High
I spoke to Ronda Vangates who is coordinating this workshop. The workshop is scheduled for Wednesday, May
8, 2002 at the Hyatt Hotel, Jasmine Room, 400 SE 2nd Avenue, Miami at 2:30 p.m.
-----Original Message -----
From: Davis, Yolanda
Sent: Tuesday, April 30, 2002 9:57 AM
To: Lagace, Rita; Thompson, Priscilla A.; Scheider, Sylvia; Rojas, Anna
Subject: FW: Workshop on Wednesday, May 8, 2002
Importance: High
Good morning Rita, please submit information regarding venue to get the advertisement published and also, so that we
can get the venue set-up for audio (by our Communications Department). Thank you.
yoli
-----Original Message -----
From: Davis, Yolanda
Sent: Monday, April 29, 2002 1:18 PM
To: Lagace, Rita
Cc: Scheider, Sylvia; Rojas, Anna
Subject: Workshop on Wednesday, May 8, 2002
Importance: High
Rita, please note the undermentione. .,,id confirm venue, including suite #, etc. fo, .. ris advertisement. Thank you.
DISTRICT 5rA A MOTION DIRECTING THE
CITY MANAGER TO SCHEDULE A WORKSHOP ON WEDNESDAY, MAY 8,2002,2:30 P.M. FOR THE
CITY COMMISSION TO CONSIDER PRIORITIES OF BOND FUNDS; FURTHER DIRECTING THE
MANAGER TO SCHEDULE ALLOCATIONS OF THE BOND FUNDS FOR THE COMMISSION
MEETING OF MAY 9, 2002. Note for the Record: The location of this workshop was later identified as the
Knight Center. MOTION 02-468 MOVED:
TEELE SECONDED: SANCHEZ UNANIMOUS
Scheider, Sylvia
From: Thompson, Priscilla A.
Sent: Monday, April 29, 2002 7:26 PM
To: Davis, Yolanda
Cc: Scheider, Sylvia
Subject: Notice for Bond Workshop
Importance: High
As you can see from the information below, the City Clerk's office has to notice the Commission's
up coming Bond Workshop.
Please draft an appropriate notice for my review for the workshop using the language listed below
and any other pertinent information you deem necessary.
I would appreciate seeing such a draft by tomorrow afternoon so that we can meet the required
scheduling deadlines.
-----Original Appointment -----
From: Vangates, Ronda A. On Behalf Of Gimenez, Carlos
Sent: Thursday, April 25, 2002 12:41 PM
To: Thompson, Priscilla A.; Vilarello, Alejandro; Gimenez, Carlos; Iglesias, Genaro "Chip"
Subject: FW: Municipal Bond Workshop
When: Wednesday, May 08, 2002 2:15 PM -6:15 PM (GMT -05:00) Eastern Time (US & Canada).
Where: Hyatt Hotel -- Room Location to Be Announced
Madame Clerk:
Once the room location has been confirmed, please take the steps necessary to
properly notice this meeting. It is anticipated that more than one member of the
City of Miami commission will be in attendance. Additionally, please have your
staff prepared to record this meeting and provide a transcript upon request.
I will provide you with the location ASAP.
Ronda
-----Original Appointment -----
From: Vangates, Ronda A. On Behalf Of Gimenez, Carlos
Sent: Thursday, April 25, 2002 12:35 PM
To: Gimenez, Carlos; Department Directors; City Manager Department; Vilarello, Alejandro; Thompson,
Priscilla A.
Subject: Municipal Bond Workshop
When: Wednesday, May 08, 2002 2:15 PM -6:15 PM (GMT -05:00) Eastern Time (US & Canada).
Where: Hyatt Hotel -- Room Location to Be Announced
Purpose of Meeting: In November of 2001, the voters of Miami approved the
Homeland Defense/Neighborhood Improvement Bond Issue. This meeting will
workshop all the potential bond projects and allow for detailed inquiry by the
elected leadership of the City of Miami.
Please come prepared to answer any and all questions that pertain to a
proposed project that your office may be involved in. Your participation and
preparation for this meeting is key to providing our leadership with information
they need to make important policy decisions regarding this issue.