RESOLUTION NO. 03— 680
A RESOLUTION OF THE MIAMI CITY COMMISSION
AUTHORIZING AN INCREASE IN THE CONTRACT WITH
UNITECH BUILDERS, CORP., FOR THE
CONSTRUCTION OF THE NEW RECREATION BUILDING
AT JOSE MARTI PARK, IN AN AMOUNT NOT TO
EXCEED $100,000, FROM $1,518,720 TO
$1,618,720, TO COVER THE COSTS OF
UNANTICIPATED ADDITIONAL CONTRACT COSTS;
ALLOCATING SAID FUNDS FROM CAPITAL
IMPROVEMENTS PROJECT NO. 331419 FOR SAID
INCREASE; FURTHER AMENDING RESOLUTION
NO. 02-902 TO REFLECT A DECREASE IN FUNDS
ALLOCATED FOR PROJECT EXPENSES, IN AN AMOUNT
NOT TO EXCEED $100,000, FROM $457,673.20 TO
$357,673.20, THEREBY MAINTAINING TOTAL
ESTIMATED PROJECT COSTS OF $1,976,393.20;
AUTHORIZING THE ALLOCATION OF FUNDS FROM
CAPITAL IMPROVEMENTS PROJECT NO. 331419 IN
ADDITION TO CAPITAL IMPROVEMENTS PROJECT
NO. 331385 FOR THIS PROJECT; AND AUTHORIZING
THE CITY MANAGER TO EXECUTE THE NECESSARY
DOCUMENTS, IN A FORM ACCEPTABLE TO THE CITY
ATTORNEY, FOR SAID PURPOSE.
BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI,
FLORIDA:
Section 1.
An increase
in the contract
with UNITECH
Builders, Corp.,
approved by
Resolution No.
02-902, for
construction of a new recreation building at Jose Marti Park, in
RESCINDBD
REPEALED
CITY COSI► sfflom
MEETING OF
JUN 1 2 ?nn3
Resolution No.
03- 680
an amount not to exceed $100,000, from $1,518,720 to $1,618,720,
to cover the costs of unanticipated additional contract costs,
is authorized, with funds allocated from Capital Improvements
Project No. 331419 for said increase.
Section 2. Resolution No. 02-902 is amended in the
following particulars to decrease funds allocated for expenses,
in an amount not to exceed $100,000, from $457,673.20 to
$357,673.20, thereby maintaining total estimated project costs
of $1,976,393.20:1
"RESOLUTION NO. 02-902
Section 1. The bid of Unitech Builders Corp.,
the lowest responsive and responsible bidder pursuant
to Invitation for Bids No. 01-02-136, dated June 4,
2002, in the proposed amount of $1,518,720 for the
project entitled "Jose Marti Park Recreation Building,
B-3258" for the Total of Base Bids 1 through 16 of the
proposal plus six (6) Additive Alternate Items, based
on Lump Sum and Unit prices, is accepted at the price
stated therein.
Section 2. An increase in the contract for
unanti.cipatea auaitional contract costs for
construction of the new recreation building, in an
amount not to exceed $100,000, from $1,518,720 to
$1,618,720, is authorized.
1� Words and/or figures stricken through shall be deleted. Underscored
words and/or figures shall be added. The remaining provisions are now
in effect and remain unchanged. Asterisks indicate omitted and
unchanged material.
Page 2 of 4
03- 680
Section 2-3. The total estimated project costs
of $1,976,393.20 are allocated from Capital
Improvements Project Nos. 331385 and 331419, as
apprepriated by the Annual Apprepriatiens and Gapital
Imp re v ement Pre-j e e t s—Grdinan ees , as amend
Section 44. The total project costs consist of
the $!,5!8 8 $1,618,720 for contract costs and
$45:7,673.29 $357,673.20 for estimated expenses
incurred by the City.
Section 3. The City Manager is authorized' to execute
the necessary documents, in a form acceptable to the City
Attorney, for said purpose.
Section 4. This Resolution shall become effective
immediately upon its adoption and signature of the Mayor.11
The herein authorization is further subject to compliance with
all requirements that may be imposed by the City Attorney,
including but not limited to those prescribed by applicable
provisions of the City Charter and Code.
a� If the Mayor does not sign this Resolution, it shall become
effective at the end of ten calendar days from the date it was
passed and adopted. If the Mayor vetoes this Resolution, it
shall become effective immediately upon override of the veto by
the City Commission.
Page 3 of 4
a)3— 680
PASSED AND ADOPTED this 12th day of
ATTEST:
j�- -4 a� 4� 7 -
PR SCILLA A. TH PSON, CIT CLERK
VILARELLO
ATTORNEY
W7288:tr:BSS
AND CORRECTNESS:
June 2003.
Page 4 of 4 o)3-
680