HomeMy WebLinkAboutR-03-0571J-03-304
03/19/03
RESOLUTION NO. 03— 571
A RESOLUTION OF THE MIAMI CITY COMMISSION,
WITH ATTACHMENT(S), BY A FOUR-FIFTHS (4/5 THS )
AFFIRMATIVE VOTE, RATIFYING, APPROVING AND
CONFIRMING THE CITY MANAGER'S FINDINGS OF AN
EMERGENCY(S), WAIVING THE REQUIREMENTS FOR
COMPETITIVE SEALED BIDDING PROCEDURES AS
DESCRIBED ON THE EXHIBITS) ATTACHED AND
INCORPORATED; ALLOCATING FUNDS FROM THE
BUDGETS OF VARIOUS USER DEPARTMENT ACCOUNTS.
BE IT RESOLVED BY THE COMMISSION OF THE CITY OF MIAMI,
FLORIDA:
Section 1. By a four-fifths (4/5th,) affirmative vote,
the City Manager's findings of an emergency(s), waiving the
requirements for competitive sealed bidding procedures as
described on the exhibit(s) attached are ratified, approved and
confirmed, with funds allocated from the budgets of various user
department accounts.
CITY COMUSSION
MEETT TG OF
Resolution No,..
03- 5 • 1
Section 2. This Resolution shall become effective
immediately upon its adoption and signature of the Mayor.!'
PASSED AND ADOPTED this 22nd day of May , 2003.
MANUEL A. DIAZ, MAYOR
In accordance with Miami Code Sec. 2-36, since the Mayor did not indicate, approval of
this Iraislation by sigmin0 in the dcsign, pl2ce prc
bouornes effective wiNl :h,. (110) days frorn
regarding same, without the IViayor exercising a vote.
• J Jm�/ tet,
ATTEST: Pri illy A. Thompson, City Cerk
PRISCILLA A. THOMPSON
CITY CLERK
...
9JANDR0 VILARELLO
TY ATTORNEY
W7113:tr:MJC
AND CORRECTNESS:
�i If the Mayor does not sign this Resolution, it shall become
effective at the end of ten calendar days from the date it was
passed and adopted. If the Mayor vetoes this Resolution, it shall
become effective immediately upon override of the veto by the
City Commission.
Page 2 of 2
03- 571
FROM
CITY OF MIAMI. FLORIDA
�Nw INTER -OFFICE MEMORANDUM IN
Carlos A. Gimenez
City Manager
Alberto Ruder
Director
of Parks and Recreation
00-01-196
June 28, 2001
CATE F
SUBJECT. Emergency Roof Repair
West End Park -�
REFERENCES: Purchase O er No. 219235 3 1
ENCLiDSURS-3.
On May 21, 2001, you authorized the Department of Parks and Recreation to proceed on an
emergency basis with informal bidding to award a contract to the lowest responsible bidder to
repaidreplace the tile roof at West End Park. At that time, 54,000.00 was identified as a
contingency in the event additional funds were needed to replace damaged wood that could not
be seen until the original roof was removed. The contract was subsequently awarded to FZ
Roofing Contractors of Miami with its bid of $52,900.00, and Purchase Order No. 219235 was
established on May 30, 2001. Funding was identified from Community Development Block
Grant funds. It should be noted the 54,000.00 contingency funds were not included in Purchase
Order No. 219235.
Between May 30 and June 14, 2001, FZ Roofing Contractors of Miami began work on the
project. They discovered extensive termite -infested and water -damaged wood in need of
replacement. The total cost of replacing the 4" x 8" tongue -in -groove plywood and insulation
exceeded the original $4,000.00 contingency fund by $12,110. 10, totaling S 16,110.10.
Therefore, we are requesting authorization to increase Purchase Order No. 219235 by 516,110.10
for a total expenditure of 569,010.10. It would be our intention to have this ratified at the earliest
possible City Commission Meeting. Should this meet with your approval, please indicate by
signing below.
J -03-304 APPROVE
qwl�rmen i Manager
W7113
DATE: 6 ' B o
AR/FKR/eo
c: Frank K. Rollason, Assistant City Manager
Linda M. Haskins, Director, Department of Management and Budget �11�a"
Pilar Saenz, C.I.P. Administrator, Department of Management and Budget
John Jackson, Director, Department of Public Works
Gwendolyn Warren. Director. Department of Community Development
03- 571
CITY OF ANA:: c FLOaI-
INTER-OFFICE MEMORANDUM
Carlos A. Gimenez _ May 17, 2001 T A
City Manager
s . Emergency Roof Repair
West End Park
Alberto Ruder. Directs - -
Parks and Recreation Department
This memorandum serves to request your authorization to proceed on an emergency basis with informal
bidding to award to the lowest responsible bidder, a contract to repair/replace the We Toot at West End Park
(250 SW 606 Street). We believe that these repairs are of an emergency nature because the park is
heavily utilized and the roof has severe roof leaks, which are impacting our recreation program.
Additionally, our Summer Programs is scheduled to com nence on Am 18. 2001 and we want to do
everything possible to replace the roof so that it will not interfere with our Summer activities. The
Department of Parks and Recreation has contacted three (3) companies and have obtained two
quotations(one of the three companies did not bid). The blowing is a summary of the quotes:
Contractor Proect w- Amount ft.--
F2 Roofing Contracts West End
$52,900.00
V. V. Roofing, Inc (Local) West End
$60,500.00
Best Property Services (local) West End
No Bid
Plus Contingency
$4,000.00-
4,000.00-This
Thisproject may require additional funds to cove the cost of replacing additional
damaged wood that can only be identified
when the old roof is removed.
Funding to cover this emergency has been identified from Community Development Block Grant Funds.
This item win be placed on the next available Commission Agenda for ratification as soon as possible after
the work is completed.
Should this meet with your approval. please indicate by signing below:
Approved as being an 1' file ity Development Block Grant expenditure.
s r7 -DI
Approved: Date:
Gw4bi arren. Director
Community Devqopment Department
03- 571
CDBG Funding Approval: v' Date: S 2+ Av
rank K Roitaso i.
Assistant City Manager
CIP Funding Approval: Date:
"I nz �uP
CI ' trator /�
Budget Dept.. Approval: Date: G
lr Linda M. Haskins, Director
Approval: Date: �{
Carts
City Man
.VARIER Iag
c: Frank K. Rollason, Assistant City Manager
Linda Haskins, Management 6 Budget Department Director
Pilar Saenz, Management 3 Budget Department CIP Administrator
John Jackson, Public Works Department Director
Gwendolyn Warren, Commundy Development Department Director
03- 571
-J-1
7 3'
GITY OF MIAMI FL(JRInA .- _
- �
INTER•OFF10E MEMOR,,40UM 99-00-225
Tc • Carlos A. Gimenez DATE May 19. 2000
City Manager I
sua,ECT Emergency Repairs/
l Hadley Olympic Pool
`ROM Alberto Ruder REFERENCES
.� Department of Parks and Recreation ENCLOSURES
A ►�„�;
The Department of Parks and Recreation respectfully requests your approval, on an
emergency basis, .to sandblast and recoat the pool shell of the Hadley Park Olympic pool
in an amount not to exceed 560,000. Funds are allocated for this purpose, in Capital
Improvement Project No. 3 1394 1, Hadley Pool—Hurricane Irene. These repairs as well as
others that are currently in process at this facility are a result of damage incurred during
Hurricane Irene. We contacted four companies and obtained informal quotations, and
Malibu Pools has quoted the lowest price as indicated below. These repairs include at
minimum, the sandblasting and recoating of the pool shell. Additional expenses may be
incurred due to unforeseen conditions that may only be identified when the work is in
progress. That is why, we are requesting authorization for $60,000 even though the
lowest bid received is for S52,500.
The work at the Hadley Park pool must be done if the City wants to open the pool on
time for the commencement of our summer season swimming programs. The existing
condition of the shell is unsafe and prevents us from operating the pool.
Resolution No. 99-812 authorizes the City Manager to award emergency contracts related
to damage caused by Hurricane Irene. However, said Resolution Iimits the contract
award to 550,000. Consequently. we will be presenting legislation at'the next available
Commission meeting, after completion of the work, to ratify this emergency action.
Budget Approval: City Managers Approval:
An}t" Luie Brennan, Interim Director
Department of Management & Budget
FR/AR/mp
J -03-303
W7112
City
F.lq
03- 5'71