CHANGE PROPOSAL REQUEST #1
ADDITIONAL WORK ORDER
April 19, 2019
To: Brian Zeltsman
Southeast Overtown/Park West - CRA
Project Manager,
819 NW 2nd Avenue
Miami, FL 33136
Tel: 305-679-6827
Fax: 305-679-6835
2019
Email: BZeltsmanAa miami ov.com
Dear Mr. Brian.
1600 N.W 3RD AVENUE,
BLDG. D4
NIMMI, FL 33136
Project: St Peter's catholic Church
40 Year Recertification
Location: 1811 NW 41' Court
Miami, FL 33136
Contract Date: December 11th,
Per recent conversation and understanding, we hereby submit the following change proposal as requested in connection
with the named project for your approval.
Addition
1. Additional Bathrooms: Provide new rear toilet, accessible from inside the building $ 7,500
2. HVAC Replacement: (Per Engineer recommendations)
Original scope was to repair existing units; however, they are non -repairable and beyond
useful life span. New (4) 5ton HVAC units was recommended by the Engineer. $10,800
3. Replace all Interior doors: Replace aluminum storefront French door and (2) others
that were inoperable and could not be repaired $ 3,200
4. Vandalism/Theft: Replace with new all broken lights, stolen copper pipes, and
vandalized electrical conduits and wires $ 4,000
5. Security: Additional exterior lighting and monitoring system for safety and security $ 4,500
6. Bell Tower: Improvement to bell tower roof $ 5,000
$35,000
Total Change Proposal #1 $35,000.00
Time Extension: These changes require additional TBD days to the contract.
READ APPROVED AND ACCEPTED THIS day of , 20_
PROJECT MANAGER: CONTRACTOR:
Sign & Date
Page 1 of 1
Sign & Date
40 Year Certification
Additional Scope of Work
St Peter's Catholic Church — 1811 NW 4th Court
ADDITIONAL BATHROOM
Provide new rear toilet, accessible from inside the building
Install framing and drywall enclosure for accessible toilet
Supply and install sewer and water connection, water closet and pedestal
Furnish and install new 70CFM exhaust fan in ceiling with switch and wiring
Furnish and install ceramic floor and wall tiles to US standard and quality
REPLACE EXISTING HVAC
Furnish and install new (4) 5ton A/C units (i.e. - air handler and condenser units)
Supply and install new duct work
Furnish and install new refrigerant lines and covers, drain lines, and A/C stands
Exterior condenser units to be protected by security screen.
REPLACE INTERIOR FRENCH DOOR
Furnish and install aluminum storefront French door and (2) others that were inoperable and
could not be repaired
Supply and install new commercial lockset and hardware
Provide new framed opening for French door
VANDARLISM/THEFT
Remove and dispose vandalized conduits, wires, HVAC copper pipes, and exterior lights
Install new electrical service wire connections to A/C and exterior lights
Replace and or repair damaged electrical wall conduits.
SECURITY
Supply and install additional LED exterior light fixture at front entry and around the building
Furnish and install new conduits and associated wiring for new security monitoring system
Exit signs as required for all doors
BELL TOWER
Pressure clean metal bell tower
Treat with rust-oleum copper base
Apply two (2) coats liquid copper coatings made with real copper flakes