HomeMy WebLinkAboutOMNI-CRA-R-00-0035RESOLUTION NO. OMNI/CRA R-00-35
A RESOLUTION I) AUTHORIZING THE COMMUNITY
REDEVELOPMENT AGENCY ("CRA") TO PROCEED
WITH AN RFP FOR THE SELECTION OF A GENERAL
CONTRACTOR TO CONSTRUCT THE PHASE I(A) AND
I(B) IMPROVEMENTS OF MARGARET PACE PARK,
CONSISTING OF DEMOLITION, SHORELINE
STABILIZATION, SITE GRADING, STORM WATER
MANAGEMENT, WATER SYSTEMS, SANITARY
SYSTEMS, ELECTRIC SYSTEMS, SITE PAVING AND
WALLS, PERGOLA, TENNIS COURTS, VOLLEYBALL
COURTS, BASKETBALL COURT AND PAVILLION,
VITA COURSE, SECURITY BUILDING, SITE
LIGHTING, LANDSCAPING AND IRRIGATION, IN
ACCORDANCE WITH THE PLANS AND
SPECIFICATIONS PREPARED BY BERMELLO,
AJAMIL & PARTNERS, INC. ("BA') PURSUANT TO THE
PLANS DATED APRIL 21, 2000, PROJECT NO. 9999.400
(THE "PLANS"), WITH THE SUCCESSFUL
RESPONDENT AND THE CONTRACT WITH SUCH
SUCCESSFUL RESPONDENT TO BE PRESENTED TO
THE BOARD OF DIRECTORS FOR APPROVAL, AND II)
APPROVING THE CONSTRUCTION DOCUMENTS FOR
THE PHASE II IMPROVEMENTS OF MARGARET PACE
PARK, CONSISTING OF SITE PAVING, PLAY
EQUIPMENT, RESTROOMS, A RECREATION
PAVILLION, SITE FURNITURE, LANDSCAPING AND
IRRIGATION, PURSUANT TO THE PLANS.
WHEREAS, the City of Miami approved and adopted the Omni Area
Redevelopment Plan pursuant to Resolution Nos. 86-868 and 86-607 (the
"Redevelopment Plan"); and
WHEREAS, the CRA is responsible for carrying out community
redevelopment activities and projects in the Omni Redevelopment Area (the
"Redevelopment Area") established pursuant to the Redevelopment Plan; and
WHEREAS, the CRA desires to i) proceed with an RFP for the
selection of a general contractor to construct the Phase I(A) and I(B)
Improvements in accordance with the Plans, and ii) approve the construction
documents for the Phase II Improvements of Margaret Pace Park, pursuant
to the Plans
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF
DIRECTORS OF THE COMMUNITY REDEVELOPMENT AGENCY OF
THE CITY OF MIAMI, FLORIDA:
Section 1. The recitals and findings contained in the Preamble to
this Resolution are incorporated herein as if fully set forth in this Section.
Section 2. The Board of Directors of the CRA hereby i) authorizes
the CRA to proceed with an RFP for the selection of a general contractor to
construct the Phase I(A) and I(B) Improvements, consisting of demolition,
shoreline stabilization, site grading, storm water management, water
systems, sanitary systems, electric systems, site paving and walls, pergola,
tennis courts, volleyball courts, basketball court and pavillion, vita course,
security building, site lighting, landscaping and irrigation, in accordance with
the Plans, with the successful respondent and the contract with such
successful respondent to be presented to the Board of Directors for approval,
and ii) approves the construction documents for the Phase II Improvements
of Margaret Pace Park, consisting of site paving, play equipment, restrooms,
a recreation pavillion, site furniture, landscaping and irrigation, pursuant to
the Plans.
Section 3. The resolution shall be effective upon its adoption.
PASSED AND ADOPTED on this 26th day of June, 2000.
T:
r J. Fbeman/ City Clerk
Arthu? E. Teele, Jr., Chairman
2 CW,' BRA
APPROVED AS TO FORM
AND CORRECTNESS:
Lit/
Holland & Knight LLP
CRA Legal Counsel
MIA1 #946261 v2
a
tir �- • t�
3
TO: Chairman Teele and
Members of the CRA Board
FROM Robert L. Tyler T
Dir. Of Op., Admin. & Dev.
CITY OF MIAMI, FLORIDA
INTER -OFFICE MEMORANDUM
DATE: June 16, 2000
SUBJECT: Margaret Pace Park
REFERENCES: /
ENCLOSURES:
Resolutions
FILE:
RECOMMENDATION
It is respectfully recommended that the Board adopt the attached resolutions authorizing the CRA to
(i) proceed with an RFP for the selection of a contractor to construct the Phase I (A & E) improvements
of Margaret Pace Park (ii) approving the construction document for the Phase II improvements of
Margaret Pace Park in accordance with the plans and specifications prepared by Bermello, Ajamil &
Partners, Inc.
BACKGROUND
This is the first approval process of this CRA Board for the actual construction and approval of the plan
and specifications of the Margaret Pace Park project. A Cooperative Agreement between the City and
the CRA is being prepared for the role that the City and CRA will play in the administration of the
Margaret Pace Park project that is in the best interest of all concerned.
Funding Source: OMNI TIF; SNPB; FIND
Account Number: 686005.050012.4.755
686005.055012.4.746
686005.050012.4.751
ONINIICRA - _ ➢