February 17, 2021
Francisco J. Alonso, PE
Vice President
T.Y. Lin International
201 Alhambra Circle, Suite 900
Coral Gables, FL 33134
VIA EMAIL: Francisco.Alonso(a)tylin.com
RE: Vendor Non -Performance concerns regarding Contract No. 12-13-004,
Miscellaneous Civil Engineering Services
Dear Mr. Alonso:
This letter serves as the written summary of the Vendor Non -Performance Meeting held via
Microsoft Teams on February 16, 2021 at 4:00 P.M. A tape recording of the meeting is available
upon request.
The purpose of the meeting was to discuss the various non-performance issues with Contract No.
12-13-004, in particular those related to specific work orders for Golden Pines Office of Capital
Improvements ("OCI") Projects B-50412, B-50413, B50414, B50420, and B-50421.
The meeting was attended by representatives of T.Y. Lin International ("T.Y. Lin"), the Directors
of the City of Miami ("City") departments for Procurement, "OCI", and Resilience & Public Works
("R&PW'), Assistant City Managers, and the Chief of Staff for the District 4 Commission Office.
During the meeting, the City notified T.Y. Lin that any deficiencies related to missed deadlines in
achieving plan submittal milestones must be cured immediately. As a result, T.Y. Lin is to provide
one hundred percent (100%) completed plans for each of the following projects related to Golden
Pines OCI Projects B-50412, B-50413, B-50414 and B-50421, as listed in the City of Miami letter
to T.Y. Lin dated December 22, 2020, and is to submit the same to R&PW and OCI by close of
business on March 1, 2021. Please be advised that no time extensions will be granted. In order
to achieve this, T.Y. Lin has committed to increasing its current staff assigned to these
deliverables in a manner sufficient to meet the agreed upon deadline. Furthermore, T.Y. Lin is
hereby notified that any revisions to the plans directed by the City on or after March 1, 2021, must
be completed and returned to R&PW and OCI within seventy-two (72) hours of receipt of those
comments.
T.Y. Lin has indicated its commitment to curing these deficiencies. Should the City find that these
deficiencies described above are not cured within the specified timeframe of March 1 st, 2021 as
set forth in this letter, the vendor may be found in default, terminated, and the City may seek other
options. Procurement will follow up with R&PW and OCI as needed prior to the March 1, 2021
deadline in order to evaluate T.Y. Lin's progress.
Non -Performance Review Meeting, T.Y. Lin International, February 16, 2021
Page 2
Sincerely,
Annie erez, CPPO
Director of Procurement
C: Esteban Ferreiro, Chief of Staff, District 4
Fernando Casamayor, Assistant City Manager/Chief Financial Officer
Nzeribe Ihekwaba, PhD., PE, Assistant City Manager, Chief of Operations
Alan M. Dodd, PE, Chief Resilience Officer/Director, R&PW
Hector Badia, Interim Director, OCI
Juvenal Santana Jr., PE, Director, R&PW
Jorge Mora, Assistant Director, OCI
Fernando V Ponassi, MA Arch., MA PPA, Assistant Director, Procurement